Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 05/13/2004 |
MECHANICAL - INTERMEDIATE |
|
Approved |
IVRS - Inspection :*/ INSPECTED 1ST LAYER OF FIRE WRAP - OK TO PROCEED WITH 2ND LAYER. INSPECTED SUSPENDED ROUGH DUCT. OK TO SHEET ROCK. |
| 05/06/2004 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :*/ PROVIDE BACKING AROUND CEILING BOXES. INSPECTED SUSPENDED ROUGH DUCT, CONDENSATE DRAIN LINES. PROVIDE A LETTER FROM THE ENGINEER IF CHANGING FROM A FIRE RATED SHAFT TO FIRE WRAP. PROVIDE A CLEAN OUT ON GREASE DUCT AS PER MANUFACTURERS SPECS ON FIRE WRAP. INSPECTED WELDS ON GREASE DUCT. |