Inspection Status: Approved

Inspection History: GRADING - FINAL

Permit Number - T04BU03031

Inspection Description - GRADING - FINAL

Inspection Status - Approved

Date Description Inspector Results Comments
11/01/2006 GRADING - FINAL Approved
07/28/2006 GRADING - FINAL Denied 1. COMPLETE ALL ITEMS LISTED ON 10-28-06 INSPECTION PUNCH LIST.
2. PROVIDE SLOPE STABILIZATION SEE NOTE #7 ON PREVIOUS INSPECTION, INCLUDE SLOPE BETWEEN EXTRUDED CURB AND BARRICADE, AND ROCK RIP RAP SHOWN BETWEEN KEYSTONE RETAINING WALLS AS SHOWN ON THE NEWLY REVISED GRADING PLAN.
04/27/2006 GRADING - FINAL Denied 1. SUBMIT A REVISED GRADING PLAN TO THE C.O.T. ENGINEEERING DIVISION FOR REVIEW AND APPROVAL OF AS-BUILT CONDITIONS TO ADDRESS THE PREVIOUS INSPECTION COMMENTS OR CONSTRUCT TO THE APPROVED PLANS.
2. PROVIDE A LETTER OF CERTIFICATION FROM THE ARIZONA REGISTERED P.E. THAT CERTIFIES THAT THE PROJECT, R/D BASIN, AND ALL DRAINAGE IS CONSTRUCTED IN CONFORMANCE WITH THE APPROVED GRADING PLANS AND WILL FUNCTION AS DESIGNED.
3. CALL IN THE FINAL GRADING INSPECTION FOR PHASE 1 PERMIT# T04BU02006. INSPECTION TO BE COMPLETED AND APPROVED IN CONJUNCTION WITH THIS PERMITS FINAL GRADING INSPECTION.
10/18/2005 GRADING - FINAL Denied 1. BUILD TOP OF WALL TO ELEVATION 2618/FLUSH WITH CURB
(SEE DETAIL 3 PAGE C2.1)
2. PROVIDE IMPERVIOUS SOIL CAP ON 6:1 LANDINGS
(SEE DETAIL 3 PAGE C2.1)
3. PROVIDE CONCRETE COLLAR, CONTROL JOINTS AND CUT THE 24" PIPE FLUSH WITH THE WALL (SEE DETAIL 5 PAGE C2.1)
4. PROVIDE THE FIRST ANNUAL R/D BASIN CERTIFICATION LETTER FROM AZ REGISTERED P.E. PER NOTE ON PAGE C3.1
5. CORRECT PONDING WATER ON ASPHALT SURFACES (SEE FIELD PLAN).
6. PROVIDE CROSSWALK STRIPPING AT THE SOUTHEAST CORNER OF THE FELLOWSHIP HALL.
3. CLEAN-UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS.
7. PROVIDE ROCK STABILIZATION:
2:1 SLOPES = ROCK RIP RAP ON FILTER FABRIC
1:1 SLOPES = GROUTED ROCK RIP RAP
COMPLETE ALL SITE WORK AS SHOWN ON THE SITE AND GRADING PLANS.

THE FINAL GRADING INSPECTION FOR PHASE 1 PERMIT# T04BU02006 WILL ALSO NEED TO BE COMPLETED AND APPROVED IN CONJUNCTION WITH THIS PERMITS FINAL GRADING INSPECTION.
09/22/2005 GRADING - FINAL Denied NOT READY FOR INSPECTION (PHASE II)
COMPLETE ALL SITE WORK AS SHOWN ON THE SITE AND GRADING PLANS.

INSPECTION COMMENTS FOR PHASE 1 PERMIT# T04BU02006 WILL NEED TO BE COMPLETED FOR APPROVAL OF THIS PERMIT
1. PROVIDE 4:1 SLOPES ON R/D BASIN
2. BUILD TOP OF WALL TO ELEVATION 2618
(SEE DETAIL 3 PAGE C2.1)
3. PROVIDE IMPERVIOUS SOIL CAP ON 6:1 LANDINGS
(SEE DETAIL 3 PAGE C2.1)
4. PROVIDE CONCRETE COLLAR, CONTROL JOINTS AND CUT THE 24" PIPE FLUSH WITH THE WALL (SEE DETAIL 5 PAGE C2.1)
5. PROVIDE THE FIRST ANNUAL R/D BASIN CERTIFICATION LETTER FROM AZ REGISTERED P.E. PER NOTE ON PAGE C3.1