Permit: T04BU02986


Addresses:

825 W CONGRESS ST


Inspection Status: Partial Approval

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T04BU02986

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Partial Approval

Date Description Inspector Results Comments
10/23/2007 STORMWATER FOLLOW-UP INSP Partial Approval No SWPPP concerns at this time.
08/08/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor repaired and replaced controls. Spoke to Justin, explained they need to keep controls in working order with basic maintenance.
07/30/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice. Contractor has 2 days to address items:
1- Contractor needs to address wash out around site.
2- Clean streets.
3- Install controls in all catch basins.
4- Provide NOI for site.
Spoke to Justin via cell phone at approx 1340, in regards to issues. If items are not addressed will issue a notice of violation or a stop work order.
07/26/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice. Contractor has 4 days to address:
1- Contractor needs to address standing water in basin on Sembrador Ave. (longer then 24)
2- Address controls for catch basins. (repair/replace)
3- Address wattle around project. (pulled up)
4- Clean was out around site.
5- Clean streets.
If contractor does not address items I will issue a notice of violation. Spoke to Gale via cell phone at approx 1350. She asked me to leave a copy of the correction notice at the Granite trailer.
05/15/2007 STORMWATER FOLLOW-UP INSP Partial Approval Contractor address items from last inspection. Spoke to Brent super for off site work, in regards to catch basin protection.
05/03/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued correction notice, contractor has 10 days to complete:
1- Sweep Streets. (2nd notice)
2- Replace all ripped open sand bags.
3- Replace or repair wattle damaged by construction.
4- Clean all wash out from around site. (2nd notice)
5- Provide wash out area for all sub-contractor.
6- Install or replace all SWPPP controls in catch basins.
7- Repair security fence around burrow pit. (2nd notice)
8- Remove dirt remps from paved streets.
9- Clean all wash out from paved streets. (south side)
I spoke to Gale project manager for site, I explained if items are not addressed I will issue a notice of violation.
01/11/2007 STORMWATER FOLLOW-UP INSP Partial Approval 24 hours contact is Gale Marsland, Office: 393-3974, Cell: 370-3028. Met with Rick on site, contractor completed items 8 and 7 from correction notice. Contractor still need to provide controls from lots and keep wash out cleaned up.
01/09/2007 STORMWATER FOLLOW-UP INSP Not Applicable Met with Brent and walked site. Contractor to install wattle on north and northeast sides of project also along Clearwater.
Also met with Rick contractor has completed items #1,2, and 5. I told rick if they clean W. Congress St. I will not issue stop work order.
01/04/2007 STORMWATER FOLLOW-UP INSP Correction Required Issued CORRECTION NOTICE. Contractor needs to:
1- Stabilize west entrance. Track out.
2- Keep all interior streets clean. Track out from lots.
3- Water harvesting basin holding water for more then 24 hours.
4- Stop all wash out on to lots. Provide area for sub-contractors to wash out in, per SWPPP.
5- Re-install silt fence north side of project and extend west.
6- Provide SWPPP control for all lots.
7- Provide 24 hour contact for site.
8- Clean track out off West Congress St.
Spoke to Rick in regards to issues. Rick and I walked site and discussed SWPPP issues. Contractor given 10 days to clean and address issues. If items are not addressed Stop Work Order will be issued.
12/29/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Sweep all streets.
2- Clean track out on to W. Congress St.
3- Provide wash out area for all subs and ensure sub-contractor use.
4- Re-install existing controls around perimeter of project.
5- Install temp controls around building lots.
Will met with Rick on 1/4/07 at 0900 hours, in regards to SWPPP issues.
11/08/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Clean up mason and concrete wash out. Provide proper wash out area.
2- Address erosion under curb cuts.
3- Keep all SWPPP controls in working order.
Spoke to Frank with Granite, Project Manager and called Rick Ashley (975-7757) in regards to issues.
10/11/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Address items from last inspection.
2- Sweep streets.
3- Install controls around spoil material northwest corner.
Spoke to Brent and Gale in regards to.
10/09/2006 STORMWATER FOLLOW-UP INSP Correction Required Spoke to Brent in regards to track out from Congress to the on ramp to I-10. Brent said he had a sweeper scheduled for 10:30am and at 3:30pm.
09/26/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Install temp. fence around pit #2. Per approved drawing. (safety)
2- Install SWPPP controls northwest corner.
3- Make repairs to SWPPP controls around site as needed.
4- Contractor needs to install SWPPP controls in new disturbed areas.
Spoke to Brent and Gale in regards to issues, on site.
09/07/2006 STORMWATER FOLLOW-UP INSP Correction Required 1- Compact dirt berm along eastside of project.
2- Install controls in drainage channel, northeast corner of project.
Called and left message for Brent site super. No call back.
08/17/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor address some items from last inspection, continues to work on punch list.
08/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to:
1- Repair security fence.
2- Repair controls around catch basin northwest corner.
3- Repair gravel pad entrance.
4- Install controls northeast corner.
5- Install controls southeast corner. Around stock pile.
Spoke to site super in regards to control installation.
Per Mike with Granite connect to permit #T04BU02986
06/20/2006 STORMWATER FOLLOW-UP INSP Partial Approval Met with Mike on site super went over SWPPP changes. Contractor getting ready to start work a long Clearwater.
06/09/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to install concrete wash out area and ensure usage.
05/24/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Repair/replace silt fence on northwest corner. (2nd notice)
2- Install drainage channel south side of project.
Spoke to Brent site super in regards to issues. Need to watch catch basins and west side for erosion.
05/10/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Install stormwater controls around all catch basins.
2- Repair silt fence on northwest corner of project.
Spoke to Mike site super in regards to issues at approx. 1320 hours.
04/26/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor re-staked silt fence in north side of project. Contractor still needs to bury bottom of fence.
04/12/2006 STORMWATER FOLLOW-UP INSP Correction Required Repair all silt fence on north side of project.
03/24/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to repair silt fencing on northside of project (2nd. Notice). Also maintain 2' setback around perimeter of project. Contacted Rick in regards to items. Rick said he would take care of them.
03/14/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to Mike in regards to repairing silt fence on north side of project, also cleaning northwest side next to apt.
02/28/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time. Contractor to install concrete wash out area.
02/10/2006 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time.
02/02/2006 STORMWATER FOLLOW-UP INSP Partial Approval Met Rick Ashley on site to discuss changes to SWPPP. Approx. 100 ' of fence on the west side to be taken down.
01/26/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to clean silt out of parking lot northwest side of project. Talked to Rick (975-7757) via cell phone in regards to this matter.
01/12/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor addressed items from last inspection. Contractor forming up catch basins.
12/22/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to re-install drainage channel on south side of property.
2nd. Notice.
12/08/2005 STORMWATER FOLLOW-UP INSP Correction Required Met with contractor on 12/7/05 in regards to adding a construction entrance. At that time I gave Mike site super a copy of the Stormwater Ordinance.
Contractor needs to reinstall drainage channel on south side of project.
On northwest corner of project contractor may need to install stormwater controls to stop run off.
I spoke to Carlos in regards to stormwater issues.
11/16/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor waiting on temp fence before starting work in parking lot to Apt. complex. Northwest side of project.
11/02/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor addressed items noted on last inspection.
10/20/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Clean silt run off from streets in apt. complex northwest corner of lot.
2- Remove soil material from apt. complex fence, install stormwater controls south and southeast side of apt. complex property.
10/04/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor is moving material noted on last inspection. Contractor still needs to cleaning parking lot to apt. buildings. Spoke to grading foreman.
09/19/2005 STORMWATER FOLLOW-UP INSP Correction Required Spoke to Mike site super in regards to silt run off on northwest corner of property next to apartment complex.
08/25/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address:
1- Track out on to W. Congress St.
Talked to Mike project eng.
08/11/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor placed cold patch at site entrance and cleaned up gravel pad.
08/01/2005 STORMWATER FOLLOW-UP INSP Partial Approval Site looked good. I talked to Dan Ball site super in regards to sweeping up track out.