Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T04BU02884
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/26/2006 | STORMWATER FOLLOW-UP INSP | Approved | SITE HAS BEEN STABILIZED WITH THE EXCEPTION OF THE AREA RIGHT AJACENT TO ALL PAVING-HYDROSEEDING HAS BEEN ORDERED | |
04/17/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | SITE WORK CONTINUES OUTFALLS TO BASIN BEING FORMED UP BASIN ROUGH GRADED LOOKS LIKE PAVING SHOULD START END OF THIS WEEK/BEGINNING OF NEXT SITE SUPER NOT ON SITE |
|
04/04/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | TALKED TO STEVE WITH TRIUMPH BUILDERS BEFORE C OF O ALL SITE WORK MUST BE COMPLETE, INCLUDING: BASIN, PAVEMENT, CURBING, RIP-RAP, PAAL, STRIPING AND BASIN CERTIFICATION. |
|
03/23/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | MET WITH SITE SUPER AND ADVISED-ALL SITE WORK MUST BE COMPLETE BEFORE ANY C OF O WILL BE ISSUED | |
03/20/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO TRACK OUT STOCKPILE HAS BEEN MOVED BASIN CONST TO START SOON |
|
03/13/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | POST NOI/AZPDES AND SWPPP SITE IN GOOD SHAPE LITTLE TRACK OUT RETENTION WALL IN PLACE OF SILT FENCE ON WEST SIDE OF SITE CONCRETE WASH OUT NEEDS TO BE DESIGNATED |