Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T04BU02640
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/02/2008 | STORMWATER FOLLOW-UP INSP | Approved | ||
05/08/2008 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO NEW STARTS | |
11/15/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | TJ BEDNAR V-DITCH HAS BEEN PLACED AT ALL LOTS BASINS STILL APPEAR NOT TO HAVE BEEN ADDRESSED |
|
11/15/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | LENNAR SITE IS ALMOST BUILT OUT NO STORMWATER CONCERNS AT THIS TIME |
|
10/02/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO CONCERNS STANDING WATER PICS 2706-2709 |
|
09/13/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | TJ BEDNAR SECTION -ARCADIA LANDSCAPING CLEANING UP DRAINAGEWAY NW CORNER -SW CORNER STANDING WATER -NEW WASHOUT PLACED - |
|
09/13/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | LENNAR -NO WORK DONE ON SPLASH PAD LOCATIONS -5 LOTS LEFT TO BUILD OUT |
|
07/31/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | STANDING WATER IN OLDER SECTION (SIERRA PACIFIC/TJ BEDNAR) CONTROLS IN NEED OF MAINTENANCE IN LENNAR SECTION |
|
06/26/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO CONCERNS AT THIS TIME SITE ALMOST BUILT OUT |
|
05/31/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | LENNAR NO CONCERNS AT THIS TIME SITE ALMOST BUILT OUT |
|
05/31/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | SIERRA PACIFIC CURB SIDE BMPS NEEDED SWEEP STREETS |
|
05/31/2007 | STORMWATER FOLLOW-UP INSP | Correction Required | TJ BEDNAR LOT 236 SWEEP STREET AND PLACE CURBSIDE BMPS |
|
05/17/2007 | STORMWATER FOLLOW-UP INSP | Prior to 1010/1015 | NO CONCERNS AT THIS TIME ACTIVITY ON SITE HAS SLOWED WAY DOWN VERY FEW LOTS LEFT |
|
04/05/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | SITE NEEDS REGULAR SWEEPING | |
01/08/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | NO CONCERNS AT THIS TIME SITE WORK CONTINUES ALMOST BUILT OUT |
|
11/02/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | SWEEPING AND GENERAL SITE CLEAN UP | |
10/05/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | SENT EMAIL TO DREW WITH LINKS FOR INSPECTION RESULT LOOK UP AND ACCESS TO PICTURES | |
10/04/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | CORRECTION NOTICE ISSUED 5 DAYS SIGNED FOR BY JERRY -UNCONTAINED DRYWALL WASHOUT LOT 111/112 -UNCONTAINED STUCCO WASHOUT LOT 117/118 -DRYWALL WASHED OUT IN ROADWAY WEST OF LOT 6577 COOPERSTOWN -STUCCO WASHED OUT ON NORTH SIDE OF LOT 2 HOUSES EAST OF STADIUM AND COOPERSTOWN -PAINT WASHED OUT LOT 135 FROM LOT 141? -DRY WALL IN ROADWAY LOT 139 -CURBSIDE BMPS ON IN PLACE -DEBRIS/GARBAGE NOT CONTAINED THROUGHOUT SITE -CALLED DREW AND ADVISED |
|
09/18/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | CORRECTION NOTICE ISSUED 7 DAYS -LOT 131 MOVE STOCK PILE BEHIND CURB/PLACE CURBSIDE BMP -CLEAN UP TRACK OUT COOPERSTOWN/CLARKSON -CLEAN UP WASH OUT LOT 143 -CLEAN UP TRACK OUT LOT 161 -REPLACE SEDIMENT CONTROLS AT SCUPPER SPLINTER/SPLENDID -CLEAN UP WASH OUT 8027 S TALACO TRL DRYWALL/STUCCO -DRYWALL WASHED OUT LOT 49 |
|
09/05/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | CORRECTION NOTICE ISSUED 7 DAYS -NO DUMPSTER/CONSTRUCTION DEBRIS NOT CONTAINED LOT 57 AND 6640 TALACO -PLACE CURBSIDE BMPS AT ALL FOUNDATION STARTS -NO (UN-CONTAINED) STUCCO WASH OUT LOT 73/74, 29, 6640 TALACO, 35, 23 |
|
08/11/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | HAND DELIVERED 8/9 INSPECTION | |
08/09/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | -TRACK OUT/SEDIMENT SOUTH OF LOT 111 -DEBRIS/GARBAGE LOT 113/114 NO DUMPSTER -TRACK OUT/SEDIMENT IN ROADWAY EAST OF LOT 116/117 -SWEEP COOPERSTOWN -LOT 131/133 CONCRETE WASHED OUT IN STREET PICS 929-941 |
|
06/26/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | -TIPPED OVER PORTA TOILET LOT 143 -TRACK OUT AT LOT 139 -ROCK AND DIRT SPILLED OVER CURB LOT 137 (NO CONTROLS) -SIGNS OF STANDING WATER IN BASIN WEST OF LOT 151 -TIPPED OVER PORTA TOILET LOT 151 -TRACK OUT ON SPLENDID LN NEEDS TO BE SWEPT -TIPPED OVER PORTA TOILET LOT 28 -DRY WALL WASHED OUT AT LOT 25 (BARRELS NOT USED) -LEAKING/RUNNING HOSEBIB LOT 33 |
|
06/02/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | NO CHANGE IN SITE SWEEPING SCHEDULE IS FOR FRIDAY |
|
05/31/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | SWEEP STREETS (STADIUM PW/COOPERSTOWN, SPLENDID LN E OF STADIUM PW TO LADONNA) CONCRETE WASHED OUT IN FRONT OF LOT 74 |
|
05/22/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | TRASH AND DEBRIS AROUND SITE DUE TO HIGH WINDS TODAY SITE IN GOOD SHAPE OTHERWISE |
|
05/08/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | SITE IN GOOD SHAPE ISSUES FROM LAST INSPECTION HAVE BEEN ADDRESSED MET WITH DREW (SWPPP MGR) AND SPOKE TO DAVID ON SITE BE SURE CONTRACTOR DOES ALL CLEAN UP IN FRONT OF LOT 102?/103? (FOUNDATION/SLAB WORK) |
|
03/06/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | TALKED WITH LENNAR/US HOMES REPS ON SITE SANTA RITA LANDSCAPING IS IN CHARGE OF SWPPP FOR LENNAR/US HOME-THEIR PORTION OF SITE IS IN EXCELLENT CONDITION. |
|
10/10/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | SOME OF THE ROADWAYS HAVE BEEN PAVED ON THIS SITE, SEE ASSURANCE FILE FOR A LISTING OF ALL LOTS THAT CAN BE RELEASED AT THIS TIME. I WILL RECHECK THIS SITE IN THE FUTRE AFTER ADDITIONAL MATERIAL HAS BEEN PLACED. | |
08/26/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | CONTRACTOR CONTINUES TO WORK ON COMPLETING ALL OF THE UTILITY WORK, PLACEMENT OF THE CURBS, AND PREPARING THE SITE FOR THE FUTURE PAVEMENT. I WILL CONTINUE TO CHECK THIS SITE FOR PROGRESS AND FOR THE FUTURE RELEASE OF THE ASSUSRANCES. | |
07/18/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | SITE CONTINUES TO MOVE INSTALL UNDERGROUND SEWER AND UTILITIES AT THIS TIME. NO MAJOR STORM WATER CONCERNS AT THIS TIME. | |
06/06/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | This site is in the process of installing sewer lines at this time. The gunite drainage channel in the middle of the project is nearly complete at this time. No major storm water concerns at this time. Land developer for Lennar homes has been notified for the requirement of certified letters from the Engineer of record on the retention/detention basins. | |
05/10/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | THIS SITE HAS NO MAJOR STORM WATER CONCERNS AT THIS TIME. THE SITE HAS BEGUN TO ROUGH CUT ROADS AND DEVELOPE ELEVATIONS FOR INDIVIDUAL LOTS. ALSO TOOK A LOOK AT THE OLD VISTA MONTANA ESTATES PROJECT TO OBSERVE ANY CORRECTIVE WORK BEING PERFORMED FOR THIS PROJECT. NONE OF THE PERVIOUSLY LISTED ITEMS OF CORRECTIONS FOR THIS SITE HAVE BEGUN AT THIS TIME. | |
04/12/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Some trenching is occuring along the North perimeter near the frontage road on I-10. Dirt remains inside the filter sock. No ther storm water concerns at this time. | |
03/23/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | No storm water concerns at this time. Initial grading is still being developed at this time. |