Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T04BU02571
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/09/2005 | STORMWATER FOLLOW-UP INSP | Approved | All areas stabilized. | |
12/02/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor sealing parking lot. All areas have been stabilized. Contractor given copy of drainage letter standard. |
|
11/14/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Super Ron given copy of Stormwater Ordinance. 1- Clean silt off streets. 2- Install stormwater controls around spoil piles. 3- Reinstall stormwater controls east side of project. 4- Contractor needs to schedule inspection for cleaning and final installion of catch boxes around site. |
|
10/27/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Items that need to be addressed: 1- Clean track-out on the northside of site. 2- Contain deteriorating straw bales. 3- Install stormwater controls northside of site, also return current controls to working order. 4- Contractor will need to schedule a inspection when stormwater boxes are cleaned and concrete place around. Per contract drawing 202B. Spoke to Ron site super in regards to issues. |
|
10/14/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to keep up with general maintenance on site. Also discussed the moving of the H.C. ramp 10 feet the east to meet slope conditions. Will meet on site Monday 10-17-05 at 1000 hours with super and engineer. | |
09/29/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | No concerns at this time. Trash and silt in street but contractor is sweeping site. |
|
09/08/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor has cleaned catch basins out and made repairs to silt fence. Contractor has started to clean silt out of street and parking lot. Contractor still needs to finish sweeping street and parking lot and replace straw bales. Contractor to call in a re-inspection for 9-14-05 Wed. |
|
09/06/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor has made no correction from last visit. Items are: 1-Clean silt off street and parking lots. 2- Repair aor replace silt fence. 3- replace hay bales as needed. 4- clean catch basins. 2nd. notice. Talked to Ron site super. |
|
08/16/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Clean silt off street. 2- Repair or replace silt fence. 3- Replace hay bales as needed. New site super Ron Dixon cell 623-628-6607. |
|
07/18/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Talked to super in regards to repairing silt fence on eastside of property and replacing sand bags around catch basins. |