Inspection History Details
Permit: T04BU02490
Inspection Status: Approved
Inspection History: GRADING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/31/2008 | GRADING - INTERMEDIATE | Approved | ||
| 01/09/2007 | GRADING - INTERMEDIATE | Partial Approval | SITE WORK IS COMPLETE FINAL GRADING INSPECTION IS WAITING FOR REVISED GRADING PLAN. |
|
| 08/22/2006 | GRADING - INTERMEDIATE | Not ready for Inspection | 1. COMPLETE ALL SITE WORK 2. PROVIDE A LETTER OF CERTIFICATION FROM THE ARIZONA REGISTERED P.E. OF RECORD, THAT CERTIFIES TAHT THE PROJECT, RETENTION/DETENTION BASIN AND DRAINAGE WAS CONSTRUCTED IN CONFORMANCE WITH THE APPROVED PLAN AND WILL FUNCTION AS DESIGNED. 3. PROVIDE 24' PAAL OR SUBMIT REVISED PLANS TO C.O.T. ENGINEERING FOR REVIEW AND APPROVAL. 4. COMPLETE ALL SOIL AND SLOPE STABILIZATION. 5. CALL IN FINAL GRADING INSPECTION #09190 FOR TO4BU02490. |
|
| 08/21/2006 | GRADING - INTERMEDIATE | Not ready for Inspection | 1. COMPLETE ALL SITE WORK. 2. PROVIDE A LETTER OF CERTIFICATION FROM THE AZ REGISTERED P.E. OF RECORD THAT CERTIFYS THAT THE PROJECT, R/D BASIN AND DRAINAGE WAS CONSTRUCTED IN CONFORMANCE WITH THE APPROVED PLAN AND WILL FUNCTION AS DESIGNED. 3. PROVIDE 24' PAAL OR SUBMIT REVISED PLANS TO C.O.T. ENGINEERING FOR REVIEW AND APPROVAL. 4. COMPLETE ALL SOIL AND SLOPE STABILIZATION. 5. CALL IN FINAL GRADING INSPECTION #09190 FOR T04BU02490. |
|
| 08/08/2006 | GRADING - INTERMEDIATE | Not ready for Inspection | PROVIDE TRUNCATED DOMES AT ALL PEDESTRIAN WALKWAYS OR SIDEWALKS THAT CROSS VEHICULAR TRAVEL AREAS. THIS PROJECT MUST COMPLY WITH ADA REGULATIONS. |