Permit: T04BU02261

Parcel: 13822023A

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
09/15/2008 GRADING - FINAL Approved contractor addressed punch list
08/29/2008 GRADING - FINAL Correction Required Met on site with Fred site super in regards to erosion and vegetation in basin. Fred needs to address erosion on basin walls and cuts vegetation in basin before final approval.
07/21/2008 GRADING - FINAL Partial Approval Provide letter addressing elevation on lots # 14, 15, 16 and 17. Address erosion in basin (N/E corner). Spoke to Larry in regards to.
05/14/2008 GRADING - FINAL Partial Approval Spoke to John Evans in regards to punch list. John asked if sediment marker had to be installed. I told John if its on the approved drawings it needs to be installed. If not he will need to go to 201 N. Stone and have deleted.
05/06/2008 GRADING - FINAL Partial Approval Contractor addressed items 9 and 10.
05/06/2008 GRADING - FINAL Partial Approval Went over punch list with Fred site super, I told Fred I would fax him a copy by the end of the day.
05/01/2008 GRADING - FINAL Denied Punch List:
1- Stabilize all areas disturbed by construction.
2- Repair trench settlement lot #6.
3- Repair erosion in Detention/Retention Basin.
4- Clean bleeder pipe in Detention/Retention Basin.
5- Install Sediment indicator in Detention/Retention Basin, per page 2 of approved drawings.
6- Stabilize side slope on lot #14 next to driveway.
7- Have all changes to drawings approved at 201 N. Stone.
8- Have engineer address pad elevations for lots #14, 15, 16 and 17.
9- Install Detention/Retention Basin inlet on east side per page #1 of approved drawings.
10- Have Grading permit un-expired at 201 N. Stone.
Spoke to Fred site super for this project in regards to punch list, also faxed copy to Fred.
07/23/2007 GRADING - FINAL Correction Required Basin holding water for more then 24 hours.
04/17/2007 GRADING - FINAL Partial Approval Dowles OK, Contractor can place concrete for spillway.
03/27/2007 GRADING - FINAL Continued Met with contractor, they are finishing the basin slopes to a 4:1 PER PLAN AND BUILDING THE CONCrete outfall from the basin. I told the conctractor that he should use dowles to tie the new conc. to the existing channel. He said he would, also he will use a 1ftX1ft toe down in basin.
11/22/2006 GRADING - FINAL Denied A preliminary grading inspection was performed and the following must be completed prior to calling for a final grading inspection.
1) Remove all construction debris and dirt stockpiles from lot 10
2) Repair trench settlement on lot 6
3) Install chain link fence to grade at entrance adjacent to drainage channel.
4) Remove vegetation and silt from the basin.
5) Repair basin slopes and grade to 4:1 per plan.
6) Remove straw bales from basin.
7) Repair chain fence in basin
8) Construct basin outlet spillway per plans.
9) Provide an engineering cert. for basin.
10) clean outlet pipe from basin.
11) Repair erosion at inlet channel to basin.
12) re-establish and line drainage channel with rip rap from the cul-de-sac to basin inlet.
09/20/2006 GRADING - FINAL Partial Approval Basin continues to hold water.
08/01/2006 GRADING - FINAL Correction Required Detention basin holding water.