Permit: T04BU02261

Parcel: 13822023A

Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Date Description Inspector Results Comments
09/15/2008 STORMWATER FOLLOW-UP INSP Approved all areas stabilized
10/26/2007 STORMWATER FOLLOW-UP INSP Not Applicable No activity on site at this time. Contractor did form up last driveway.
12/14/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor continues to work on punch list.
10/23/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time. Small amount of dirt in street.
10/04/2006 STORMWATER FOLLOW-UP INSP Partial Approval 1 Lot left. Contractor needs to cut vegetation in basin.
08/30/2006 STORMWATER FOLLOW-UP INSP Partial Approval Small amount of wash out needs to be cleaned up. Spoke to Fred Majors in regards to. Fred said a homeowner was placing concrete and made the mess. Fred said he would contact the homeowner to get it cleaned up.
08/14/2006 STORMWATER FOLLOW-UP INSP Partial Approval Basin holding water for more then 24 hours. Contractor will need to proform post perk. test. Spoke to Nancy on site in regards to issues.
08/01/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address:
1- Basin holding water.
2- Repair erosion next to driveway. Front of 716.
07/18/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to clean wash out off street. Spoke to Cody onsite in regards to. Detention basin holding water, pictures taken.
06/16/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time.
06/05/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor cleaned up wash out and removed AB from street.
05/18/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to:
1- Clean street.
2- Clean stucco and mason wash out around site.
3- Remove AB from street or install controls around.
05/04/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to stake down wattle on basin inlet.
04/20/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to clean up wash out noted on last inspection. Site nearing close out. Spoke to Nancy in regards to letter from engineer addressing drainage ways and basin. I also noted engineer will need to address lots on the southeast corner of project that are not built per the approved drawing. All drainage from these lots is to the rear, not the front as on the approved drawings.
04/05/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to provide proper wash out area for stucco subs. Clean wash out infront of 710. Reinstall wattle in basin inlet.
03/17/2006 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to provide the proper wash out area for masons and concrete workers. Contractor needs to clean wash out infront of 716.
03/07/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to clean street.
02/16/2006 STORMWATER FOLLOW-UP INSP Partial Approval Spoke to Nancy in regards to staking down waddle at basin inlet, also keeping silt off the streets. If silt gets any worse street will need to be cleaned.
02/03/2006 STORMWATER FOLLOW-UP INSP Partial Approval No stormwater concerns at this time. Contractor still needs to clean out basin.
01/20/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to stack down waddle at basin inlet. Also contractor needs to clean silt out of basin.
01/05/2006 STORMWATER FOLLOW-UP INSP Partial Approval Contractor continues to install block wall along south side of project. Contractor still needs to clean out basin.
12/15/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor has approx. 300' of block wall to install. Also contractor starting to clean out basin. (Not finished)
12/01/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor starting block wall on southeast side of project.
Talked to Fred Major in regards to lots 15, 16 and 17. Lots can not drain per the grading plan. Contractor will need to note this on as-builds and in drainage letter before release of assurances.
11/14/2005 STORMWATER FOLLOW-UP INSP Correction Required 1- Contractor needs to stabilize area on southwest corner of project.
2- Protect basin inlets.
Walked site with Fred Majors owner of Major Constraction, went over lot drainage on southside of property. Also talked to Fred in regards to concrete spilway called out on drawings.
10/27/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor needs to address:
1- install protection around bleeder pipe in detention basin.
2- install proper stormwater controls southwest side of site. Near intersection of Santa Clara and Carol Christine.
3- Protect basin inlet.
4- Replace or repair controls southside of site east of basin.
5- Repair erosion around basin.
Spoke to Cody and Nancy with Major Construction in regards to issues. A Correction Notice was issued. Contractor given 5 days to make repairs. If repairs are not made in 5 days a Stop Work Order will be issued.
10/19/2005 STORMWATER FOLLOW-UP INSP Correction Required Repairs noted on last inspection un-acceptable.
No one on site.
10/07/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor stop making repairs to stormwater controls. Contractor still needs to to protect wash on southwest corner of property and at bleeder pipe. Some of these items where first noticed on 6-27-05.
09/29/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor has made some repairs to silt fencing and installed straw bales in basin inlet. Contractor making repairs to stormwater controls along Santa Clara and CarolChristine.
Contractor still needs to protect bleeder pipe in basin.
Site super Cody said he will be done with all work by Friday 10-7-05 and would like me to schedule an inspection for Friday 10-7-05 at 0900.
09/14/2005 STORMWATER FOLLOW-UP INSP Correction Required Contractor has made no correction to detention basin or stormwater controls in last 3 visits. (8-16-05)
If items are not addressed a stop work order may be issued.
Talk to Nancy in office about issues.