Inspection History Details
Permit: T04BU02197
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/11/2015 | STORMWATER FOLLOW-UP INSP | Approved | ||
| 09/04/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor continues to work on punch list. Contractor installed channel in basin and cleaned. | |
| 03/30/2007 | STORMWATER FOLLOW-UP INSP | Approved | All areas stabilized. Contractor need to complete grading punch list. | |
| 02/27/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | All areas have been stabilized. Contractor needs to call in final inspections. | |
| 01/24/2007 | STORMWATER FOLLOW-UP INSP | Partial Approval | Clean up wash out in front of 1945. (dry wall) Spoke to dry wall and site super in regards to issue. | |
| 12/22/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to: 1- Clean up paint wash out northeast corner of project. Paint. 2- Clean track out off streets. Spoke to site super in regards to items. |
|
| 10/26/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Clean up lot 11, stucco wash out. | |
| 10/05/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address paint and drywall wash out around site. Spoke to Otis via cell phone. | |
| 09/22/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Keep trash picked up around site and clean around wash outs. | |
| 09/05/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Clean wash out infront of lot 36. | |
| 08/15/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Spoke to Otis in regards to; Keeping Pinal Vista clean and making repairs to concrete wash out area. 3rd. Notice. | |
| 08/07/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor made repairs to concrete wash out area and cleaned Pinal Vista. | |
| 08/02/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | 2nd. Notice 1- Keep Pinal Vista clean. 2- Clean and repair wash outs. 3- Fill weep holes on east basin wall. Spoke to Otis site super via cell phone in regards to issues. |
|
| 07/20/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Keep Pinal Vista clean. 2- Clean and repair wash outs. 3- Fill in weep hole on east basin wall. Spoke to site super in regards to items. |
|
| 06/20/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to clean Pinal St. and pick up trash on south side of project. | |
| 06/07/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | No stormwater concerns at this time. Contractor started homes along southside of project. | |
| 05/22/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to fill weep holes on east wall of basin. | |
| 05/08/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor address retaining wall and slope on lot 40 (3to1). Left message for Eric (349-2645) in regards to filling weep holes on east basin wall. | |
| 04/25/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Spoke to Mike Gardner at approx. 1315 in regards to stabilizing slope on southeast corner of project and backfill retaining wall on northest corner. Forgot to talk to Mike about contractor needing to fill in weeps hole on east basin wall. | |
| 04/07/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to: 1- Provide location of SWPPP. 2- Contractor needs to stabilie slope on eastside of lot 40. |
|
| 03/21/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to address item #3 from inspection on 2-27-06. | |
| 03/09/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor addressed items #1 and #2 from last inspection. | |
| 02/27/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Met on site with Mike Gardner with SPH. Contractor to address items noted on last inspection. 1- Contractor to stabilize area on north side of block wall. 2- Contractor will install wash out area. 3- Contractor to provide area onsite for SWPPP. 4- Contractor to contact subs and keep them off property to the north or provde letter of for easement. | |
| 02/24/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Stop subs from accessing project from property on north side. Contractor will need to provide a easement and stabilize area disturded. 2- Install concrete wash out area for masons and concrete workers. 3- Reinstall waddle on northside of project. 4- Provide SWPPP. 5- Post NOI. |
|
| 02/07/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to: 1- Clean up trash. (blowing off site) 2- Clean up concrete wash out. (outside grading limits) 2nd. Notice. 3- Address waddle northwest corner of project. (starting to break apart) 4- Install concrete wash out area. E-mailed Mike Gardner in regards to issues, on 2/7/06 at approx. 1425. |
|
| 01/24/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Waddle buried northwest corner of project. 2- Clean up concrete wash out dumped outside grading limits. (N/E) 3- Install concrete wash out area. Sent e-mail to Mike Gardner in regards to these issues. Message recieved at 2:39pm 1/24/06. |
|
| 01/12/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor addressed items from last inspection. | |
| 12/19/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Items: 1- Contractor needs to clean dirt and broke apart waddle off street eastside of project. (Kramer Ave.) 2- Contractor needs to clean concrete wash out northeast side of project. Outside grading limits. 3- Repair waddle northwest side of project. 4- Schedule Stormwater Follow up inspection when items are complete. |
|
| 12/05/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | No concerns at this time. Contractor grading roadways. |
|
| 11/15/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Asked contractor (Eagle Rock) to move a waddle back into place on the northeast side along curb. | |
| 10/28/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Clean track-out on Kramer Ave. 2- Install controls on southside of project. 3- Stormwater controls on northwest side starting to come apart. 4- If contractor continues to use eastside of project as an entrance a construction entrance will need to be installed. |
|
| 10/17/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Waddle is breaking apert on northwest side. Needs repairing. | |
| 09/07/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Control silt along Pinal St. Control track-out on to Campbell Ave. |
|
| 08/15/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Repair or replace waddle on northside of property. 2- Pull material off and back from waddle, northside of property. 3- Have a copy of SWPPP on site with grading plan. I met with Mike Gardner on site in regards to these issues. Mike was given a copy of the correction request and told me he would have the SWPPP on site by Wednesday 8-17-05. The other items would be taken care of tomorrow 8-16-05. Contractor will need to schedule re-inspection when items are addressed. |