Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/31/2005 | GRADING - FINAL | Approved | Contractor completed punch-list. | |
| 08/12/2005 | GRADING - FINAL | Correction Required | Punch-list for Nighthawk Trucking: 1- Repair asphalt at scupper outlet. 2- Fill holes arould ballards. 3- Clean up all construction debris. 4- Submit engineer stamped copy of asbuilts. 5- Submit letter from engineer in regards to basins. |
|
| 08/10/2005 | GRADING - FINAL | Correction Required | Met with Wade the site super. Contractor needs to address these items before C of O will be approved. 1- Repair asphalt on streetside of scupper. 2- Fill holes around ballards. 3- Provide drainage for north basin. (holding water) 4- Clean up all construction trash. |