Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER INSTALL OF CONTROLS
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/03/2005 | STORMWATER INSTALL OF CONTROLS | Approved | ALL STORM WATER CONTROLS HAVE BEEN INSTALLED. POST NOI AND/OR AZPDES AUTHORIZATION NUMBER AT ENTRANCE TO SITE. ANY SIGNIFICANT CHANGES TO THE SWPPP MUST BE APPROVED AND SHOWN ON SWPPP DRAWING. MAINTAIN STORM WATER CONTROLS AS NEEDED. PERFORM STORM WATER INSPECTIONS PER SWPPP AND DOCUMENT THEM. |
|
| 02/17/2005 | STORMWATER INSTALL OF CONTROLS | Partial Approval | Ensure stabalized construction entrance is installed. Post AZPDES authorization number and/or NOI on site as per plan. Any significant changes to SWPPP shall be approved by the engineer of record. Establish a concrete washout when needed. No other storm water concerns at this time. |