Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T04BU01884
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/06/2006 | STORMWATER FOLLOW-UP INSP | Approved | Site has been stabilized. | |
03/29/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor placed hydroseed for phase II. | |
03/20/2006 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to stabilize phase II. No activity on phase II for 70 days. Contacted Wade site super in regards to stabilizing phase II. Wade said it would be completed on Wed. 3/22/06. | |
03/09/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to stabilize phase II. | |
02/17/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | CONTRACTOR NEEDS TO STABILIZE PHASE II | |
02/06/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor needs to stabilize phase II. | |
01/23/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor still needs to stabilize area in phase II. | |
01/09/2006 | STORMWATER FOLLOW-UP INSP | Partial Approval | Controls in place. Contractor still needs to stabilize area in phase II. |
|
12/16/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to install waddle in curb opening per new SWPPP plan. Spoke to Wade site super via cell phone at approx. 0950. | |
12/02/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | No concerns at this time. Contractor framing storage units. | |
11/15/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | No one on site. Contractor needs to install stormwater controls or Stabilize area that has been cleared and grubbed | |
09/29/2005 | STORMWATER FOLLOW-UP INSP | Cancelled | ||
09/15/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to address: 1- Construction entrance pad. Not working. 2- Clean up track-out on to street. 3- Reinstall waddle in front of catch basin northside of property. |
|
08/23/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contractor needs to repair pr replace silt fence and waddle as needed. Contacted Wade the site super and informed him. Via cell phone at approx. 1045 hours. |
|
08/10/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Contracor needs to: 1- Clean up all track out and silt run off. 2- Provide positive flow on northeast corner of property to stop run off. |
|
07/05/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | Contractor installed waddle across catch basin on north side of the property per last inspection on 6-27-05. Contractor needs to re-install slit fence on east side of property next to open trench. | |
06/27/2005 | STORMWATER FOLLOW-UP INSP | Correction Required | Walked site with Wade Bingham, site super. Silt fencing needs replacing or repairing in various locations, catch basin on north side of property needs to be capped, slit fence or waddle to stop slit entrusion to catch basin. |