Permit: T04BU01206


Addresses:

7130 S MCKINLEY AV

Inspection Status: Approved

Inspection History: ENGINEERING PRE-CONSTRUCTION

Date Description Inspector Results Comments
07/13/2006 ENGINEERING PRE-CONSTRUCTION Approved MET WITH:
HABITAT FOR HUMANITY, PATRICK PITTMAN 326-1217 XTN 220
DOUCETTE, BRETT RIDDLE 954-1628
DOUCETTE, ROGER PILMORE (SWPPP) 225-9616
TJ BEDNAR, KEVIN FITZSIMMONS 349-4467
TJ BEDNAR, LARRY SCHROEDER 248-1574
AMERICA BUILT, JOSHUA SWINNEY 730-5861
AMERICA BUILT, ALISSA OTT 790-6566
EARTHWORKERS, STEVE SLEIGHT 609-8046
RICHMOND AMERICAN, JASON SALINE 904-5518
07/10/2006 ENGINEERING PRE-CONSTRUCTION Scheduled MEETING SCHEDULED 7/13 10 AM ON SITE
JASON SALINE RICHMOND AMERICAN
ALISSA OTT AMERICA BUILT 790-6566
PATRICK PITTMAN HABITAT FOR HUMANITY 326-1217 XTN 220
ED CRADDOCK TJ BEDNAR
JIM VANCE DOUCETTE 240-3120 NOT ABLE TO ATTEND

POSSIBLITY OF EARTHWORKERS BEING CONTRACTED
03/04/2005 ENGINEERING PRE-CONSTRUCTION Partial Approval THIS SITE HAS THE CORRECT CONTROLS INSTALLED AND IS IN GOOD CONDITION. NO OTHER STORM WATER CONCERNS AT THIS TIME.
11/10/2004 ENGINEERING PRE-CONSTRUCTION Not ready for Inspection NO ACTIVITY ON THIS SITE AT THIS TIME.