Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/01/2005 | GRADING - FINAL | Approved | ||
| 06/21/2005 | GRADING - FINAL | Denied | 1. PROVIDE A WATER HARVEST BASIN IN THE LANDSCAPE AREA ON THE WEST PERIMETER OF SITE IN LIEU OF CUTTING THE OTHER CURB. ROCK RIP RAP MUST BE INSTALLED FLUSH WITH PAVEMENT GRADE AND ALLOW POSITIVE DRAINAGE INTO THE WATER HARVEST AREA. 2. CLEAN-UP AND REMOVE ALL CONSTRUCTION MATERIAL AND DEBRIS. 3. PROVIDE COVERS OVER OPENINGS TO FOUNDATION OF PRE-FAB BUILDING. 4. GRIND DOWN TRIP HAZARD (PIPE) AT SOUTHWEST CORNER OF BUILDING. 5. FINISH GRADE ADJACENT TO SIDEWALK NEAR NORTHWEST CUT IN SITE WALL. 6. PROVIDE BICYCLE PARKING AS SHOWN ON THE DEVELOPMENT PLAN. 7, BACKFILL EXCAVATION AT GAS METER AND REMOVE SOIL FROM A/C UNIT SLAB. |
|
| 05/31/2005 | GRADING - FINAL | Partial Approval | This site is still under a temporary C of O until final grading punch-list items are addressed. |