Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/25/2005 | GRADING - FINAL | Approved | Contractor needs to: 1- Paint ballards inside trash enclosure. 2- Finish raking down detention basins. |
|
| 07/22/2005 | GRADING - FINAL | Denied | DENIED SEE PUNCH LIST FROM 7/20/05 | |
| 07/21/2005 | GRADING - FINAL | Denied | See punch-list from 7-20-05. Went over punch-list items with contractor. |
|
| 07/20/2005 | GRADING - FINAL | Denied | Contractor needs to address these items: 1- Finish all site work. 2- Install bike rack. 3- Grout bollards in trash encloser and paint. 4- Finsh parking lot. 5- Install HC signs. 6- Repair curb around parking area. 7- Install curb stops. 8- Install detention basins (2). Contractor to re-schedule for Friday 7-22-05, 3:00 PM. |
|
| 06/29/2005 | GRADING - FINAL | Denied | Site not ready for inspection. Asked contractor to give one week notices for final inspection. |