Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Inspection History Details
Inspection Status: Approved
Inspection History: STORMWATER FOLLOW-UP INSP
Permit Number - T04BU00396
Inspection Description - STORMWATER FOLLOW-UP INSP
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/24/2005 | STORMWATER FOLLOW-UP INSP | Approved | I MET WITH DAVID THE SUPERINTENDENT FOR THIS PROJECT REGARDING THE CONSTRUCTION OF THE DRAINAGE SWELL LEADING ON-SITE DRAINAGE INTO AN EXISTING CHANNEL ON THE N. SIDE OF THE PROJECT. I EXPLAINED THE NEED TO HAVE SOME OF THE LOOSE DIRT PULLED BACK FROM FALLING INTO THE CHANNEL. HE EXPLAINED HE UNDERSTOOD THE CORRECTION NEEDED AND THAT I WOULD BE BACK TO INSPECT THE WORK WITHIN THE NEXT WEEK WHEN THE WORK IS TO OCCUR. | |
03/22/2005 | STORMWATER FOLLOW-UP INSP | Partial Approval | I spoke with the superintendent David regarding some of the drainage improvements for the A-Atlas Storage. The onsite drainage will exit the N. end of the project and into an existing dirt drainage channel. I will be meeting with him onsite on 3/24/05 to discuss concerns with the construction and final product of the drainage swell leading to the drainage channel. | |
12/21/2004 | STORMWATER FOLLOW-UP INSP | Approved | INSPECTED SITE FOR GRADING AND EROSION, SPOKE TO FORMAN ABOUT FINAL GRADING CONCERNS | |
06/25/2004 | STORMWATER FOLLOW-UP INSP | Partial Approval | Site is in good condition with no storm water concerns at this time. | |
06/07/2004 | STORMWATER FOLLOW-UP INSP | Partial Approval | Site is stable and has no other storm water concerns at this time. |