Permit: T04BU00159

Parcel: 14025006A


Addresses:

5720 S RANDALL BL


Inspection Status: Approved

Inspection History: STORMWATER FOLLOW-UP INSP

Permit Number - T04BU00159

Inspection Description - STORMWATER FOLLOW-UP INSP

Inspection Status - Approved

Date Description Inspector Results Comments
12/22/2005 STORMWATER FOLLOW-UP INSP Approved Contractor completed all work.
12/14/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor completed grading, to call in finial grading inspection and C of O on Monday 12/19/05.
12/01/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor given copy of Stormwater Ordinance.
Wayne Aderson new super on site. Cell 488-6278.
11/10/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor going to install check dam in basin area. Sub dumped spoil pile in basin.
10/27/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor wants to watch spoil pile on southside of property for run off.
10/13/2005 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time. Contractor has graded around detention basin area.
09/28/2005 STORMWATER FOLLOW-UP INSP Partial Approval No concerns at this time.
09/13/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor installed sewll around southside of property to stop run off and tied swell into detention basin.
Spoke to super in regards to basin walls. If walls are 4 to 1 or steeper and more then a 2 feet in depth a barrier of some type is needed.
09/01/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor needs to watch for:
1- Track-out and silt on streets.
2- Keep positive flow onto property along south edge. Waddle or silt fence may need to be installed.
08/18/2005 STORMWATER FOLLOW-UP INSP Partial Approval Contractor using detention basin as concrete wash out area. Contractor needs to maintain positive flow on southside of property. If positive flow is lost contractor will need to install stormwater controls to stop run off.
08/02/2005 STORMWATER FOLLOW-UP INSP Partial Approval Talked to BJ site super about keeping track out cleaned up.