Inspection Status: Compliance
Inspection History: FOLLOW UP CODE VIOLATION
| Date |
Description |
Inspector |
Results |
Comments |
| 01/11/2005 |
FOLLOW UP CODE VIOLATION |
|
Compliance |
VERIFIED THAT CODE COMPLIANCE PERMITS ARE FINALED OK TO CLOSE EXCEPT FOR BILLING. BIFF BAKER FENCE CO. WAS CALLED TODAY TO REMOVE THE FENCING. |
| 11/09/2004 |
FOLLOW UP CODE VIOLATION |
|
Violation |
WORK IN PROGRESS - UNITS ARE BEING LEFT UNSECURED, CITY INSTALLED FENCE AFTER FIRE. SEND NOV FOR REPAIR WORK TO UNITS 125-130 & 225-230 |
| 08/10/2004 |
FOLLOW UP CODE VIOLATION |
|
Violation |
f.u. 60 days |
| 05/18/2004 |
FOLLOW UP CODE VIOLATION |
|
Violation |
FU FOR 90 DAYS. |
| 03/05/2004 |
FOLLOW UP CODE VIOLATION |
|
Violation |
UNITS SECURED. FU FOR 60 DAYS. |
| 02/05/2004 |
FOLLOW UP CODE VIOLATION |
|
Revision |
NO PERMIT YET, OWNER WORKING WITH INSURANCE COMPANY AND ARCHITECT TO GET PLANS READY. STILL SECURED. FU FOR 30 DAYS. |
| 01/02/2004 |
FOLLOW UP CODE VIOLATION |
|
Violation |
NO REPAIR STARTED YET, STILL SECURED & FENCED FU FOR 30 DAYS. |
| 12/01/2003 |
FOLLOW UP CODE VIOLATION |
|
Violation |
NO PERMIT AS OF 12/01/03. FIRE DAMAGED UNITS STILL VACANT & BOARDED UP. NO ACTIVITY YET FU 30 DAYS. |
| 10/08/2003 |
FOLLOW UP CODE VIOLATION |
|
Violation |
APTS 125&225 HAVE BEEN DESTROYED BY FIRE THE FLOOR BETWEEN 1 & 2 FLOOR, ALL ELECTRICAL, MECHANICAL PLUMBING AND STRUCTURAL HAS BEEN DESTROYED INCLUDING THE ROOF ON THE 2 FLOOR. THE LANDING ON FLOORS 1 & 2 HAVE BEEN DESTROYED EXTENDING TO APTS 127&227. THE MAIN WATER LINE FEEDS THREE APTS INCLUDING THE FIRE DAMAGED ONE. 11:50 P.M. SPARTAN PLBG ATTEMPTING TO ISOLATE DAMAGED BLDG WHICH HAS 12 APTS WHICH HAVE ALL BEEN VACATED, ALSO FEEDING 2 OTHE BLDGS. TOTALING 48 APTS. DAMAGED BLDG WILL HAVE TO BE FENCED. PERMITS FOR ALL PHASES WILL BE REQUIRED. |