| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/29/2006 | PLUMBING - FINAL | Approved | IVRS - Inspection :* | |
| 03/26/2003 | PLUMBING - FINAL | Denied | IVRS - Inspection 0999*ALL EXTERIOR CLEAN OUTS SHALL COMPLY WITH SECTION 719.5 UPC. | |
| 03/13/2003 | PLUMBING - FINAL | Partial Approval | IVRS - Inspection 0000* 1.) WORK EXCEEDS SEWER REPAIR. 2.) CONTRACTOR HAS EXPOSED AND REPLACED ALL OF THE BLDG. DRAIN INSIDE THE CIRCLE K STORE CAST IRON ROTTED AWAY BLDG DRIAN IS CURRENTLY STUBBED JUST OUTSIDE BLDG TO CLEANOUT AND IS UNDER TEST. ABS BLDG. DRAIN IS INSTALLED OK WATER TEST OK OK TO COVER. 3.) CONTRACTOR WILL EXPOSE ABOUT 50' OF TRENCH TO TIE NEW ABS SEWER BACK INTO EXISTING CAST IRON. 4.) CONTRACTOR IS TO INSURE THAT ALL NECESSARY PERMITS ARE SECURED BEFORE COMPLETING BLDG. SEWER. |