Inspection Status: Approved
Inspection History: ELECTRIC - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/31/2003 |
ELECTRIC - FINAL |
|
Approved |
IVRS - Inspection 0000*SENT TO TEP ON 08/01AM |
| 07/30/2003 |
ELECTRIC - FINAL |
|
Denied |
1) PER NEC ART 250-24. THE GROUNDING ELECTRODE CONDUCTOR MUST BE CONNECTED TO THE GROUNDED SERVICE CONDUCTOR (NEUTRAL) AT THE SERVICE DISCONNECTING MEANS. CHANGE THE GROUNDING CONDUCTOR FROM THE SUB PANEL TO THE MAIN DISCONNECT GROUND BAR. INSTALL THE BONDING SCREW. SEPARATE NEUTRALS AND GROUNDS AT SUB PANEL 2) BOND BUSHING IS NEEDED ON CONNECTOR FROM METER CAN TO MAIN DISCONNECT. THIS CONNECTION REQUIRES A SEALING LOCKNUT OR MYERS HUB 3) CORRECT AND RECALL |