Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
Permit Number - T03CM05655
Inspection Description - PLUMBING - ROUGH, SOIL
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2004 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 08/26/2004 | PLUMBING - ROUGH, SOIL | Denied | IVRS - Inspection : See detailed listing on site.| 999*/DENIED PROVIDE PERMIT CARDS WITH CORRECT ADDRESS AND HAVE CORRECT ADDRESS POSTED AT SITE ON BUILDINGS. |
|
| 08/20/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :8"SAR 35.4 PSI AIR TEST FROM MANHOLE#1 TO MANHOLE#2 OK HANDROLL PULL FROM MANHOLE#1 TO MANHOLE#2 OK 8"SAR 35 4#PSI AIR TEST FROM MANHOLE#3 TO MANHOLE#4 INCLUDING 4"HCS CONNECTION TO NORTHWEST CORNER 5' FROM BUILDING HAS TRANSITION TO 4" DUCTILE IRON 10' EACH SIDE OF CROSSING 1' UNDER 8" 900 WATER MAIN, THIS REQUIRES CITY APPROVED DETAIL DRAWING AT BOTH WEST SIDE LOCATION STILL NEED VACUUM TESTING OF ALL MANHOLES AND AIR TEST ON 4" FROM MANHOL #4 TO SOUTHWEST BLD, HCS CONNECTION |
|
| 08/19/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/ 1) MANHOLE #3 TO MANHOLE #5 4 PSI AIR TEST ON 8" SDR 35 AND (2) 2) 4" SDR 35 LATERALS TO 5' FROM BLDG OK 3) MANHOLE #2 TO MANHOLE #3 4 PSI AIR TEST ON 8" SDR 35 OK | |
| 08/16/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/04/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :NEW MANHOLE #1 ON EXISTING 10", 8" DUCTILE IRON UP STREAM TO MANHOLE #2, 8" SDR35, UPSTREAM TO MANHOLE #3, 8" SDR35 UP STREAM TO SOUTH TO MANHOLE #4, 8" FROM SDR35 MANHOLE #3 TO EAST MANHOLE #5 OK WILL NEED TO SEE IN WRITING CERTIFICATE OF CONFORMANCE (PIMA cOUNTY) OR LETTER FROM THOM STATING IS NOT NECESSARY CONTRACTOR TO AIR TEST PIPING & VACUUM TEST MANHOLES AT LATER DATE NEED FITTINGS INSTALLED FOR HCS CONNECTIONS NEED REVISED CITY APPROVED PLAN FOR HCS PIPING CROSSING WATER MAIN ON WEST SIDE OF BUILDIN (2) LOCATIONS WILL NEED TO SEE MANDREL PULL AT LATER DATE |
|
| 07/27/2004 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :*NOT READY. PRE-CON MEET WITH SITE SEWER INSTALLER. |