Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: T03CM05561

Parcel: 11415008V


Addresses:

8080 S HOUGHTON RD


Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Permit Number - T03CM05561

Inspection Description - PLUMBING - ROUGH, SOIL

Inspection Status - Approved

Date Description Inspector Results Comments
04/27/2005 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection :* REVISED CITY APPROVED PLAN ON SITE.
03/29/2005 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
02/17/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :* PARTIAL APPROVAL 4" GREASE WASTE TO GREASE TRAP WATER TEST OK. 4'' DRAIN FROM GREASE TRAP TO SANITARY SEWER WATER TEST OK. 3" VENT FROM GREASE TRAP WATER TEST TO 2' ABOVE FINISH FLOOR OK. 1) PROVIDE WATER TEST ON GREASE TRAP DUE TO DAMAGE TO INLET OF TANK. 4" HCS CONNECTION AT NORTHEAST END OF BUILDING OK
02/14/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :* WATER HEATER 4" FLOOR SINK DRAIN AT COOLING TOWER OK ( UNDERGROUND)
02/11/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
02/10/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
02/08/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*
01/26/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :* PARTIAL APPROVAL TRENCH DRAINS IN NORTH WEST ?? PER PLAN OK
01/24/2005 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
01/21/2005 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
01/19/2005 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999* ISTALL 2-3" FLOOR DRAINS. PER YOUR APPROVED PLAN FOR TRENCH DRAIN AT DAIRY COOLER OR HAVE REVISED CITY APPROVED PLAN.
01/12/2005 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :* WATER TEST TRENCH DRAIN AT ?? BOX & PIPE WRAPS THIS AREAS OK
12/29/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/COMBINATION WASTE & VENT ON NORTH WEST SECTION UNDERGROUND WATER TEST OR PER HIGHLIGHTED & INITIALED PLAN ON SITE. 1) WILL REQUIRE CITY APPROVED REVISED PLAN OF ALL RED LINES AND ADDITIONAL FIXTURES
12/21/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/WATER TEST UNDERGROUND ONLY SOUTH WEST 4" SANITARY DRAIN FOR SF-SINK, QWC, SINGLE RESTROOM, AND (2) GANG REST ROOM WITH 2" DRAIN CONTINUATION FOR FLOOR SINK TO BE INSTALLED AT LATER DATE PER HIGHLIGHTED & INITALED PLAN IN TRAILER.
12/13/2004 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*
12/13/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :* WATER TEST UNDERGROUND GREASE WASTE & SANITARY WASTE PER HIGHTLIGHTED AND INITALED PLAN PAGE P-2
12/09/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/4" BUILD DRAIN ON WEST END OF BUILDING PER HIGHLIGHTED AND INITALED ON P-2
12/08/2004 PLUMBING - ROUGH, SOIL Partial Approval IVRS - Inspection :*/UNDERGROUND WATER TEST ON WASTE & VENT SHOWN ON REVISED CITY APPROVED PLAN P-2 FER HIGHLIGHTED AND INITALED
12/03/2004 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection :
See detailed listing on site.| 999*
12/02/2004 PLUMBING - ROUGH, SOIL Not ready for Inspection IVRS - Inspection :*/ 1) PLEASE HAVE A CITY APPROVED PLAN OF YOUR BLDG ON SITE AT TIME OF INSPECTION