Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - TEMPORARY SERVICE
Permit Number - T03CM05561
Inspection Description - ELECTRIC - TEMPORARY SERVICE
Inspection Status - Approved
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/13/2005 | ELECTRIC - TEMPORARY SERVICE | Approved | ELECTRICAL CONTRACTOR RESPONSIBLE TO KEEP ENERGIZED PARTS SAFE, AND LOCK OUT UN-INSPECTED WORK CALLED IN FIR 5/13/05 1) UFER APPROVED PER ROBERT SUBA. 2) SES OK TO ENERGIZE. 3) HDPB OL TO ENERGIZE. 4. TRANSFORMER TM OK TO ENERGIZE 5) PNL BOARD LDPA OK TO ENERGIZE. 6) PNLS CPA, CPB, CLA, CPC OK TO ENERGIZE. ELECTRICAL CONTRACTOR TO LOCK OUT ALL UNINSPECTED WORK AND GET OK PRIOR TO ENERGIZING ANY OTHER WORK. 7) SES CHANGE ON CONDUCTORS TO COPPER OK BY ENGINEER LETTER. 8) WATER -GAS-SPINKLER-STEEL-UFER APPROVED. |