Permit: T03CM05561

Parcel: 11415008V


Addresses:

8080 S HOUGHTON RD

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
05/11/2005 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection :*
03/10/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* FOOTING FOR CART CORRAL OK
03/09/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* YOU NEED TO HAVE SPECIAL INSPECTOR LEAVE, AT SITE, COPIES OF HIS FIELD REPORT.
03/04/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
02/23/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* DOCK WALL FROM 4-5
02/22/2005 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
02/01/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* PARTIAL AROUND BREAKROOM , F-G/9-10
01/24/2005 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
01/19/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
01/10/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*P LINE 7/FG
01/06/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*/SEE YESTERDAYS NOTES
01/05/2005 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*/9 EACH SPREAD FOOTINGS LINE 22
12/28/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) SPREAD FOOTINGS AROUND FREEZER (AREA G-F)
12/27/2004 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
1) 8' LINE F/1-3; TOP LINE 1 D-E
12/23/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
1) G-E SPREAD FOOTING OK
12/13/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/10/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*/LINE F 2-4 (SPEC INSP MAY CONFIRM FINISHING REPORT @2.7?)
12/09/2004 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
12/08/2004 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
12/03/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*
12/02/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :P LINE 5/F-G AND LINE F/4.8-5
12/01/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*/LINE G 5.2-6.8
11/26/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :ISOLATED FOOTINGS LINES 4-8, LINE 1 C-E
11/24/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*/ISOLATED SPREAD FOOTINGS LINES 2,3,4 & 9 OK
11/23/2004 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
11/22/2004 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :*
11/19/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*/ 1) LINE A/1-5, LINE 1/A-B (VERBAL OK FOR 2-#6 IN LIEU OF 1-#7)
11/18/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :LINE A/3-5 OK
11/17/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :* LINE A 6-10; LINE F 7-10.
11/16/2004 EXCAVATION/LAYOUT REBAR & ZON Not ready for Inspection IVRS - Inspection :REF 2/SD1 FOR SLAB DOWELS @ OPENEINGS LINE I
PROVIDE CONTINOUS FOOTING STEEL LINE F @ 8.9,7.2,9.2,9.8 OR RFI
FINISH VERTS LINE A
11/15/2004 EXCAVATION/LAYOUT REBAR & ZON Partial Approval IVRS - Inspection :*