Inspection Status: Approved
Inspection History: MECHANICAL - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 07/27/2005 |
MECHANICAL - INTERMEDIATE |
|
Approved |
IVRS - Inspection :* |
| 05/31/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* SOUTH GARAGE AREA. PRESS TEST-SUPPLY 110 PSI. RETURN 110 PSI. INCLUDES GARAGE & MESANINE AREA. LINES, FROM UND. ?? RISERS UP & OVERHEAD. |
| 05/11/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* OK FOR CEILING TILES REAR OFFICE |
| 05/05/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* OK FOR CEILING TILES ROOMS 139 THRU 144, 148, 175, 147, 136, 137, 127 THRU 132,138,133 |
| 03/29/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* CONFIRMED CHILLER PIPING IS ON A FIRM BED OF SAND. PIPE IS STRAIGHT & SLOPES TOWARDS THE MAIN BLDG OK TO FINISH BACKFILL. |
| 03/28/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* 100 LBS TEST ON UNDERGROUND CHILLER PIPE IS OK. OK TO FINISH INSULATION. PIPE NEEDS TO BE ON A FIRM BED OF SAND. REMOVE ALL DIPS & SAGS. CALL FOR INSPECTION PRIOR TO BACKFILL. |
| 03/23/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* PROVIDE A MIN. 100 LB PRESSURE TEST ON CHILLER PIPES & PROVIDE THE LISTING FOR INSULATION & OUTER JACKET ON UNDERGROUND PIPE |
| 02/15/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* OK TO SHEET ROCK HARD LIDS ALL AREAS EXCEPT ROOM 147 & CORRIDOR # 159 |
| 02/11/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* PRESSUME TEST ON UNDERGROUND CHILLER PIPE OK PROVIDE PROPER UNSULATION & JACKET FOR DIRECT BURIAL |
| 02/10/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* PROVIDE BACKING AROUND CEILING BOXES FINISH INSULATING DUCTS |
| 02/04/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* ENGINEER WILL SEND A DETAIL ON PROTECTIVE JACKET FOR UNDERGROUND CHILLER PIPING. JACKET CANNOT HAVE MECHANICAL ?? MUST BE WATER TIGHT. PROVIDE AN ADEQUATE HYDROSTATIC TEST ON PIPING |
| 02/01/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :* PROVIDE A HYDROSTASTIC TEST ON ALL CHILLER PIPING. |
| 01/14/2005 |
MECHANICAL - INTERMEDIATE |
|
Partial Approval |
IVRS - Inspection :*/PARTIAL SUSPENDED ROUGH DUCT OK TO INSULATE DUCTS |