Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
Permit Number - T03CM04982
Inspection Description - REINFORCED MASONRY PRE-GROUT
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/17/2005 | REINFORCED MASONRY PRE-GROUT | Approved | IVRS - Inspection :* | |
02/16/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* AT CMP | |
02/15/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" BLOCK @ RAMP OK | |
02/11/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* PROGRESS ON MASONRY @ RAMP OK | |
02/04/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TOP ?? TALL SITE WALLS OK | |
02/02/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* NO WEST SIDE WALLS OK TO 8' | |
01/31/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 4' S OF MECH ROOM, 4' N SIDE MAIN BLD, PARAPET TO RAMP. | |
01/26/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 4' LIFT SITE WALL BY MECH ROOM | |
01/21/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*PROGRESS ON PARAPET OK OK TO CONTINUE AS NEEDED. PARAPET SOUTH SIDE 2-7 OK | |
01/19/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* P TOP N.W STAIR / ALL PROGRESS ON PARAPETS OK | |
01/13/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
01/12/2005 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 12" BLOCK PARAPET ALONG SOUTH WALL | |
11/24/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/TAPPED OUT - I ONLY NEED TO SEE RE-PACK @ SLAB CONNECTIONS | |
11/22/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :12' @ ELEVATOR 8' STAIR LINE J - GROUT MUST BE HELD DOWN BELOW BOND BEAM ON THIS LIFT |
|
11/19/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 8' AFD ELEVATOR SHAFT, LINE J TO DECK | |
11/18/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :LINE J/2-3 @ 21' J/5-6 17' | |
11/17/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* PARTIAL 4' AFD @ ELEVATOR & STAIR J, AND LINE J TO 17'. LIGHT POLE BASES N.E. CORNER (8) EACH. | |
10/27/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
10/26/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) TOP K/14-11; A/7-10 | |
10/25/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 24" A/7-11; TOP 14 A-C AND D-H | |
10/22/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/PROGRESS ON BARRICADE OK | |
10/21/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
09/16/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
09/15/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
09/13/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
09/10/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
09/09/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
09/07/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/BUILDING #2 8' @ E PILASTERS 16' N & W 01015-REVIEW CAP HEAD STEEL |
|
09/01/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | CHANGED FROM APPROVED TO PARTIAL PER VOICE MAIL LEFT BY LEE RAY ON MY PHONE 9/01/04 | |
08/27/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :LIFT @ NW STAIR OK | |
08/25/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 12'-8" SOUTH STAIR WALL AT 1-A | |
08/24/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
08/19/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* TOP @ STAIR | |
08/17/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
08/06/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 12'-8" STAIR AREA A-2 2) 8'-8" AREA E-2 INFILL | |
08/04/2004 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :*/ 1) 4' LINE 2/E-F, 78P LINE 2/H-J AND 8' STAIR AT A/1-2 | |
08/03/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
07/30/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) LINE 2 TOP F-G AND 26' G-I, LINE A TOP 5-6 | |
07/29/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) TOP LINE 1; 12' LINE 2/G-I, 16' LINE 2 F-G | |
07/28/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) LINE 12'/F-G AND 8'/G-J | |
07/27/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :TOP 1/A-D TOP A/1-4 EXCEPT LINTEL TOP A/4-7 TOP F/1-2 TOP 1/E-G |
|
07/22/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :LINE A 3.5 -7 @ 16' LINE J 3.5 - 4.5 @ T.O.W |
|
07/21/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
07/20/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :16' A/6.5 R 21' 9/C-CS C.5/9-10 10 C.5-D 12' V.2/8-10 21' A/6-9 J/7-9 17' J.2/8-10 J/6-10 8/J J.2 10/ J-J.2 |
|
07/15/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*(1) TOP C-9 TO D-16 (2) 8' J/8-9.2 (3) 12' J.2/8-10. | |
07/14/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 1) 16' LINE A/7-10. 2) TOP LINE / 9-10. 3) 16' ZIG-ZAG C-9 TO D-10. ) 4' LINE J/8-9 | |
07/13/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*(1) TOP LINE J/8-92 AND 9.2/J-J.2 (2) LINE A 7-10 IN PROGRESS TO 16'. | |
07/12/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*12'8" AT A/6.9-10.1 AND C/8.5-10, 16'8" AT 10/J-J.2 AND J/8-9 AND 8/J-J.1 | |
07/09/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
07/08/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*LINE G/1-2 TO RAMP. | |
07/07/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
07/06/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* LIFT @ ELEV, LINE F/10-11, LINE 10/D-F. | |
07/02/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) LINE 7/F-H AT 16' 2) LINE 7/H-J; 1/A-B; 1/D-E.9 AND A/2.1-7 AT 12' | |
07/01/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 12' LINE 7/G-14; LINE F/10-11; LINE 10/D-F; LINE E.5/1116S AND ELEV | |
06/30/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
06/24/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
06/23/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
06/18/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 16" LINE 7/A-F. | |
06/17/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 4' LINE J/8-11. 2) 8' LINE J/2-5. 3) 12' LINE 1/A-E. | |
06/16/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) LINE 7/A-F AT 12', LINE A/1-4.8 AT 8' | |
06/11/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 4' LINE A/4*10 8' LINE 7/A-D, 4' LINE C 8.5-10 4' F-H / 13-14 | |
06/10/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* DISREGARD YESTERDAY'S NOTE ABOUT LINE 2 E-F | |
06/09/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) 8' LINE 1/A-F; 8' LINE E/1-2, 8' LINE F 1-2, 8' LINE 2/E-J OK 2) STEMWALLS AREA D-G/10-12.5 OK | |
06/08/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* STEM LINE J/1-8, 4' LINE 7, 4' LINE A/4-7 | |
06/04/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* 4' LINE 1 /A-G, LINE 2 /F-G, LINE G/1-2, LINE F /1-2, LINE 7 /A-E | |
06/02/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* ELEV STEM & STEM TO LINE 9 | |
05/27/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) STEMS OK LINE 7, LINE A, LINE J AS INDICATED 2) TOP OF ? WALL LINE 4 OK | |
05/25/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
05/24/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :* | |
05/20/2004 | REINFORCED MASONRY PRE-GROUT | Partial Approval | IVRS - Inspection :*/ 1) STEM LINE 1, LINE 2, LINE A/1-5,9 OK | |
05/13/2004 | REINFORCED MASONRY PRE-GROUT | Not ready for Inspection | IVRS - Inspection :*/ 1) CITY OF TUCSON IS REQUESTING A BREAK TEST ON 3000-F MASONRY LOCATIONS LINE A 5.9, 8.9 AND 9 & LINE J 5.9 AND LINE 2 E.5 |