Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date |
Description |
Inspector |
Results |
Comments |
| 09/10/2004 |
PLUMBING - GAS PRESSURE TEST |
|
Approved |
IVRS - Inspection :*/ 1) PRESSURE TEST OK 2) WILL CHECK FINAL CONNECTIONS AT FINAL |
| 09/03/2004 |
PLUMBING - GAS PRESSURE TEST |
|
Not ready for Inspection |
IVRS - Inspection :*/1)COMPLETE YOUR PIPING TO ROOF TOP UNITS AND RETEST SYSTEM. SLEEVING ON PIPING |
| 07/15/2004 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :*/ 1) GAS PIPING TO BE SLEEVED PROPERLY AND ROUTED OUT OF ELECTRIC SERVICE EQUIPMENT SPACE 2) WATER TEST WASTE AND VENT THRU ROOF OK 3) H20 PIPING WATER TEST OK |
| 06/30/2004 |
PLUMBING - GAS PRESSURE TEST |
|
Partial Approval |
IVRS - Inspection :* |