Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESSURE TEST
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/09/2006 | PLUMBING - GAS PRESSURE TEST | Approved | IVRS - Inspection :* 1. INSULATE "Y" & "T" FITTINGS. 2. TERMINATE EXHAUST FANS 3. INSTALL FURNACE DUCT WORK. 4. AC LINES NOT RUN 5. GAS BOND MUST BE EXPOSED AT ELEC. INTERMEDIATE 6. STOPPED INSPECTION. |
|
| 01/18/2006 | PLUMBING - GAS PRESSURE TEST | Not ready for Inspection | IVRS - Inspection :* | |
| 01/06/2006 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) PROVIDE GAS BOND 2) SECURE ALL EXTERIOR LINES PROPERLY |
|
| 03/02/2005 | PLUMBING - GAS PRESSURE TEST | Denied | IVRS - Inspection : Work is not complete enough to inspect.| 950* |
|