Permit: T03CM04670

Parcel: 138242420

Inspection Status: Approved

Inspection History: BUILDING PRE-SLAB

Date Description Inspector Results Comments
10/09/2003 BUILDING PRE-SLAB Approved IVRS - Inspection 0000*
10/08/2003 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection 0000*/ 1) ROUGH PLUMBING IS NOT PER PLAN. MASTER BATH SHOWER AND LAV 2" EXCEED 5 FEET TO MAIN DRAIN. BOTH WILL REQUIRE CLEANOUTS. YOU MUST REVISE PLUMBING PLAN AND HAVE APPROVED BY ARCHITECT OF RECORD AND CITY OF TUCSON PRIOR TO INTERMEDIATE INSPECTION. FAILURE TO DO SO WILL RESULT IN A REINSPECTION FEE. FIRST TIME
10/07/2003 BUILDING PRE-SLAB Not ready for Inspection IVRS - Inspection 0000*/ 1) RAINING-PLUMBING WET-UNABLE TO INSPECT