Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date |
Description |
Inspector |
Results |
Comments |
| 07/28/2006 |
ENGINEERING - FINAL |
|
Approved |
PER INSP COPY |
| 07/14/2006 |
ENGINEERING - FINAL |
|
Denied |
SEE NOTES FROM FINAL GRADING INSPECTION FOR PERMIT # T03BU01928 |
| 06/29/2006 |
ENGINEERING - FINAL |
|
Denied |
Final C of O denied, must complete all site work per previous inspection dated 10/31/05. Must have drainage certified by PE prior to final approval. |
| 10/31/2005 |
ENGINEERING - FINAL |
|
Partial Approval |
TEMP C OF O FOR ENGINEERING APPROVED, PERMANENT C OF O NOT TO BE GIVEN UNTIL ALL SITE WORK IS COMPLETED AND A FINAL GRADING INSPECTION FOR PERMIT # T03BU01928 IS COMPLETED AND APPROVED. |
| 08/25/2005 |
ENGINEERING - FINAL |
|
Denied |
DENIED, BLDG STILL UNDER CONSTRUCTION, NOT READY FOR OCCUPANCY. |