Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
08/04/2005 | ELECTRIC - UNDERGROUND | Approved | IVRS - Inspection :* | |
07/28/2005 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* 1) OK U.G. LIGHT POLE FEEDERS NORTH EM. AREA LAST LIGHT POLE |
|
07/27/2005 | ELECTRIC - UNDERGROUND | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) CONDUIT MUST BE AT LEAST 18" DEEP |
|
02/08/2005 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :* OK 1 1/2" & 1" PVC CONDUITS FOR PARKING LOT LIGHTING 1) FINISH LAST 20' TO BUILDING | |
09/28/2004 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :*/OK PRI U. G. CONDUIT | |
09/14/2004 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :*/ 1) POWER-DATA-MONITOR SYSTEM NURSES STATIONS 1ST FLOOR OK TO COVER | |
07/08/2004 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :*/ 1) EM POWER FROM AMBULANCE DRIVE TO THE NEW ADDITION AND TURN UP 3-3" PVC'S, 1-1 1/4" PVC AND 1-3/4" | |
06/11/2004 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :*/ 1) 3-3" PVC'S, 1-1 1/2" PVC'S AND 1-3/4" 90 DEGREE DRIVE WAY TO DRIVE WAY NORTH SIDE | |
05/19/2004 | ELECTRIC - UNDERGROUND | Partial Approval | IVRS - Inspection :*/ PVC FROM TRUCK WAREHOUSE DOCK TO PATIO WALL EAST. | |
05/06/2004 | ELECTRIC - UNDERGROUND | Not ready for Inspection | IVRS - Inspection : The smoke detectors have not been installed per code.| 165* |