| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/09/2005 | PLUMBING - ROUGH, SOIL | Approved | IVRS - Inspection :* | |
| 02/28/2005 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* PROVIDE LISTING ON GREASE INTERCEPTOR | |
| 08/31/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :* | |
| 08/30/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/PA 1)WATER RISER #1 = 3 § KITCHEN 2)WATER RISER #2 § CLASSROOM 118 3)ROUGH FOR ROOM #104 & 103 TEST OK $) WILL RECEIVE TEST ON VENTS AT TOP OUT. ALSO HCS BETWEEN BLDG DRAIN-SITE SEWER 3-LOCATION OK NOTE: DON'T FORGET FINE? CAULK IN FLOOR PENATRATION |
|
| 08/27/2004 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :*/PARTIAL ON K-2 - K-6=1ST FLOOR WILL NEED TO INSULATE & INSTALL CLOSET COLLERS TEST ON WASTE VENTS & WATER-OK AT THIS TIME. JERRY MILLER ON JOB SITE-TAP OK ACS. FOR MULTIPURPOSE BUILDING- PARTIAL TEST OK PLEASE PROVIDE APPROVAL FROM WASTE WATER FOR TAP IN WRITING FOR OUL RECORDS PARTIAL ON 4" SITE SEWER TO TODDER BUILD WILL NEED TO TIE IN TO EXISTING HCS & BLD DRAIN |
|
| 08/26/2004 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :*/NR-CALL JIM 349-5029 PLEASE PROVIDE APPROVAL FROM PIMA COUNTY WWM ON NEW LOCATION OF HCS MACHINE CUT ON ABOVE ADDRESS. I HAVE NO INFORMATION ON MINIMUM SPACING OF FIVE FT. BETWEEN TAP'S ON 1 CONNECTION PER LENGTH OF MAINLINE, AS PER MANUAL OF ENGINEERING STANDARDS AND PROCEDURES PIMA COUNTY WASTE WATER MANAGEMENT. PLEASE PROVIDE THIS APPROVAL IN WRITING BEFORE APPROVAL IS GIVEN BY THIS OFFICE. NOT READY FOR INSP TEST WYE? UPSIDE DOWN PLEASE CORRECT & CALL AGAIN RE TEST |
|
| 08/24/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/PA-PLEASE PROVIDE HISTORY ON INTERCEPTOR OK--TEST OK IN KITCHEN AREA. SOIL & GREASE SEE PLAN |
|
| 08/23/2004 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :*/NOT READY FOR INSPECTION | |
| 08/20/2004 | PLUMBING - ROUGH, SOIL | Not ready for Inspection | IVRS - Inspection :* | |
| 07/15/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/ 1) PVC UNDERGROUND AT INFANT/BATHROOMS-OK 2) WATER TEST ONE RISER TO TEN FEET-OK 3) OK TO COVER 4) AS INFERED BY CORRESPONDANCE, ALTERNATE METHODS TO ACCEPTED PRACTICES ARE APPROVED WHEN ACCOMPANIED WITH PETITION OF APPEAL. VARIENCE SHALL BE ON SITE AT TIME OF INSPECTION | |
| 06/29/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/ 1) VENT AND WASTE CONNECTION FOR SEWER EJECTION SYSTEM IS OK. 2) OK TO BACKFILL TRENCH. | |
| 05/28/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/ 1) PVC DWV UNDERGROUND INSTALLED PER PLAN. SEWAGE EJECTOR NOT INSTALLED. 2) OK TO BACKFILL. 3) SEE 807.2 94 UPC. - CONDENSATE WASTE MAY NOT BE DIRECTLY CONNECTED TO A SINK TAILPIECE. | |
| 05/19/2004 | PLUMBING - ROUGH, SOIL | Partial Approval | IVRS - Inspection :*/ WOMANS WASHROOM B-25 UNDERGROUND ROUGH TEST OK. OK TO BACKFILL. |