Inspection History Details
Inspection Status: Approved
Inspection History: EXCAVATION/LAYOUT REBAR & ZON
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/03/2005 | EXCAVATION/LAYOUT REBAR & ZON | Approved | IVRS - Inspection :* | |
| 10/06/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*/OK FTGS? @ MEMORIAL GARDEN | |
| 08/06/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 08/04/2004 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* | |
| 07/01/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*/ 1) ? ? BLDG FOOTING | |
| 06/21/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*/ 1) OK TO PROCEED | |
| 05/18/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*/ 1) 6 PIER FOOTING | |
| 05/07/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*/ 1) PLANTER FOOTING, GRIDLINE 4.5-5.5 | |
| 04/27/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :*/1) INTERIOR COLUMN 2) PARTIAL ON NORTH WEST RETAINING WALL | |
| 04/22/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* | |
| 04/18/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection : There is no access to the site.| 920* 9L-K FROM 4 TO D.5 LINE 2 FROM F TO K |
|
| 04/13/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection : See detailed listing on site.| 999* GRID LINE A.4-5, RETAINING ON WEST SIDE, LINE 3.A-C; LINE 2 A-F. 1 COLUMN FOOTING 3-D |
|
| 04/08/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* 5 COLUMNS GRIDLINE 4 & 5 J, F E NORTH EAST CORNER A-6 | |
| 04/05/2004 | EXCAVATION/LAYOUT REBAR & ZON | Partial Approval | IVRS - Inspection :* GRIDLINE A BETWEEN 3-5. GRIDLINE B & K THRU 3.5 TO 6 | |
| 03/31/2004 | EXCAVATION/LAYOUT REBAR & ZON | Not ready for Inspection | IVRS - Inspection :* |