Permit: T03CM04368

Parcel: 120060370

Inspection Status: Approved

Inspection History: EXCAVATION/LAYOUT REBAR & ZON

Date Description Inspector Results Comments
01/02/2004 EXCAVATION/LAYOUT REBAR & ZON Approved IVRS - Inspection 0000*
12/30/2003 EXCAVATION/LAYOUT REBAR & ZON Denied IVRS - Inspection 0999*/ 1) PLAN CALLS FOR 1'-10" WIDE FTGS. 2) REMOVE DIRT FOR AROUND ABS PIPING IN FOOTING AND THEN WRAP ALL PIPING TO BE IN CONTACT WITH CONCRETE 3) MAINTAIN MINIMUM 3" REBAR TO DIRT 4) MASONRY COLUMN FTGS. NOT PER APPROVED PLAN 5) PLAN CALLS FOR FTG AND STEM; YOU ARE USING MONO-POUR (HAVE PLAN CHANGED) 6) PLAN CALLS FOR 3 REBAR IN FTG AND 2 TOP OF TEM 7) STOPPED INSPECTION
12/23/2003 EXCAVATION/LAYOUT REBAR & ZON Denied IVRS - Inspection 0999*