Inspection History Details
Inspection Status: Approved
Inspection History: ELECTRIC - CONSTRUCTION POWER
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/08/2004 | ELECTRIC - CONSTRUCTION POWER | Approved | IVRS - Inspection :*/ 1) SUBJECT TO BOND AND OTHER INSPECTIONS | |
| 07/07/2004 | ELECTRIC - CONSTRUCTION POWER | Partial Approval | IVRS - Inspection :* | |
| 07/02/2004 | ELECTRIC - CONSTRUCTION POWER | Denied | IVRS - Inspection : See detailed listing on site.| 999*/ 1) PLANS CALL FOR COPPER-ALL OK WHEN INDICATED ON PLAN GROUND WIRE TO BOND BUSHINGS IN TERM CAN 1 ONE CONDUCTOR OF 1/0 COPPER CAN GO TO EACH CONDUIT BUSHING ONLY. WHEN DAISY CHAINED AS IN USING ON TO CONNECT TO TWO BUSHINGS, 3/0 COPPER REQUIRED |
|
| 06/04/2004 | ELECTRIC - CONSTRUCTION POWER | Not ready for Inspection | IVRS - Inspection :* |