Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2004 | PLUMBING - INTERMEDIATE | Approved | ||
| 09/02/2004 | PLUMBING - INTERMEDIATE | Not ready for Inspection | IVRS - Inspection :NOT INSTALLED PER PLAN 6" ABS PLAN CALLS FOR PVC CONSTRUCTION NOTE #2 CALLS FOR DIP UP TO 15' FROM BLDG 2" VENT MAY ONLY RUN 40' HORIZONTAL |
|
| 05/14/2004 | PLUMBING - INTERMEDIATE | Denied | IVRS - Inspection : See detailed listing on site.| 999*/ 1) BLDG SEWER IS OK UP TO 20' UPSTREAM OF P.L. 2) OK TO BACKFILL TRENCH. 3) MUST PROVIDE ISOLATION FOR COPPER WTR DISTRIBUTION THRU METAL STUDS. 4) SOIL WTR TEST FOR WASTE AND VENT SYSTEM IS OK. 5) AIR PRESSURE TEST ON OVERHEAD WTR DISTRIBUTION IS OK. |
|
| 03/23/2004 | PLUMBING - INTERMEDIATE | Partial Approval | IVRS - Inspection 0000*/ 1) SOIL WATER TEST IS OK 2) NOTE: MUST CALL ROUGH SOIL INSPECTION WITH ITEM #03005 WHEN INTERCEPTORS HAVE BEEN INSTALLED 3) THIS INSPECTION IS FOR 4" TRENCH DRAIN TAHT EXISTS NORTH SIDE OF BLDG ONLY. NOTE: 4" TRENCH DRAIN THAT EXITS SOUTH END OF BLDG HAS BEEN DELETED |