Inspection History Details
Inspection Status: Approved
Inspection History: ROOF NAILING
Permit Number - T03CM03878
Inspection Description - ROOF NAILING
Inspection Status - Approved
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2004 | ROOF NAILING | Approved | IVRS - Inspection :* | |
07/07/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* | |
06/15/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :*/ 1) LEDGER OVER DRESSING ROOMS ? | |
06/11/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* 1) CROWN OK, SHEATHING @ CROWN OVER MAIN ROOF OK. 2) UNDERSIDE OF CROWN MAY NEED SHEATHING RFI? | |
06/08/2004 | ROOF NAILING | Not ready for Inspection | IVRS - Inspection :* SOUTH LEDGER NEEDS AB'S 8" OF LESS FROM EACH END JAMB. | |
06/03/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* FIRE MARSHALL TO REVIEW SPRINKLER PLACEMENT UNDER CANTILEVERS. | |
06/01/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* NORTH ROOF LEDGER OK. SOUTH LEDGER STILL REQUIRES ANCHORS WITHIN 8" OF ENDS OF LEDGERS | |
05/25/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :*/ 1) FINISH NAILING STRAPS NE QUAD AT ROOF. OK TO DRY IN 2) SOUTH LEDGER AT WEST END AT BLDG HAS BEEN COVERED WITHOUT INSPECTION OF LEDGER REPAIR | |
05/21/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* | |
05/20/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :*/ 1) PULL BACK INSULATION ON NORTH AND SOUTH WALLS SO I CAN SEE PA STRAPS AND ADDED LEDGER ANCHORS | |
05/13/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* | |
05/12/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* 1) NEED TO COMPLETE PA STRAPS & REPLACE AS NECESSARY. 2) NON BEARING LEDGER REQUIRES 3/4" AB WITHIN 8" OF EACH LINTEL | |
05/11/2004 | ROOF NAILING | Partial Approval | IVRS - Inspection :* 1) AREA A-D FINISH NAILING @ PAINTED AREAS. 2) SIMPSON TIES LINE 1 REQUIRE RFI FOR REPLACEMENT |