Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T03CM03520

Parcel: 10609062C

Inspection Status: Approved

Inspection History: PLUMBING - ROUGH, SOIL

Date Description Inspector Results Comments
08/28/2003 PLUMBING - ROUGH, SOIL Approved IVRS - Inspection 0000*/1) ABS DWV UNDERGROUND OK. TIE IN TO EXISTING OK. TRANSITION FITTINGS OK. WATER TEST ONE RISER TO TEN FEET. 2) OK TO BACKFILL.
08/27/2003 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection 0999*/1) HORIZONTAL X HORIZONTAL CHANGE OF DIRECTION TO BE THRU WYE BRANCH OR EQUIVELENT SWEEP. 2) TRAP ARM MAY ONLY CHANGE DIRECTION 90 DEGREE WITHOUT ADDITIONAL CLEAN OUT. 3) BLAKE TEE ON ITS BACK UNDER SLAB NOT APPROVED. 4) AGGREGATE CHANGE OF DIRECTION MAY NOT EXCEED 135 DEGREE WITHOUT ADDITIONAL CLEAN OUT. 5) WHAT ABOUT THE TEST FOR ALL THOSE 45 DEGREE AT THE POINT OF CONNECTION. 6) PLEASE SEE NOTE ABOVE - NEED PLAN AND PERMIT. NEED LETTER ALLOWING ABS.
08/26/2003 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection 0999*/1) PLEASE READ GENERAL PLUMBING NOTES #3-A. 2) NOT INSTALLED PER APPROVED PLAN. 3) CONTRACTOR TO HAVE ALL REQUIRED PHASES OF PLUMBING ADDED TO PERMIT.
08/22/2003 PLUMBING - ROUGH, SOIL Denied IVRS - Inspection 0999*/NO ACCESS - CALLED HAROLD, NO ANSWER. PLEASE HAVE PLAN AND PERMIT ON SITE.