Inspection History Details
Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/21/2008 | PLUMBING - GAS PRESS TEST FNL | Approved | ||
| 12/31/2007 | PLUMBING - GAS PRESS TEST FNL | Partial Approval | IVRS - Inspection :* 1) ALL ITEMS CALLED OUT OK AT THIS TIME, WILL RELEASE GAS UPON BLDG FINALS |
|
| 12/21/2007 | PLUMBING - GAS PRESS TEST FNL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) SINGLE TO DBL WALL CONNECTION TO BE OPEN, CLEARED REDUCED 6" FROM TO 1" WITH DBL WALL 2) SINGLE WALL FLUE NOT ALLOWED IN CONCEALED AREA |
|
| 12/20/2007 | PLUMBING - GAS PRESS TEST FNL | Denied | IVRS - Inspection : See detailed listing on site.| 999* 1) COMPLETE TEMP PRESSURE FOR LAND LOCKED H20 HTR RELIEF 2) FINISH H20 HTR FLUE, NOT INSTALLED |
|
| 11/13/2006 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* | |
| 10/02/2006 | PLUMBING - GAS PRESS TEST FNL | Not ready for Inspection | IVRS - Inspection :* | |
| 09/22/2006 | PLUMBING - GAS PRESS TEST FNL | Denied | IVRS - Inspection : See detailed listing on site.| 999* |