Inspection Status: Approved
Inspection History: PLUMBING - SEWER HCS CONNECT
| Date |
Description |
Inspector |
Results |
Comments |
| 02/09/2004 |
PLUMBING - SEWER HCS CONNECT |
|
Approved |
|
| 11/04/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ WATER TEST OK FROM BLDG TO M.H. #5. OK TO BACKFILL SITE OF INSPECTION. |
| 10/20/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ 1) VACCUM TEST OK ON M-H #4 AND #5 2) AIR TEST OK M-H #1 AND #2, M-H #2 AND #3, M-H #3 AND #4, M-H #4 AND #5 3) NEED DATA ON M-H VERIFICATION OF GRADE. COMPLETE ? AT M-H #1 |
| 10/17/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
COMPLETE UP TO M.H. #5 - CONTRACTOR WILL TEST AT LATER DATE. OK TO COVER. NEED DATA ON M.H. |
| 10/16/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
1) 126' EAST OF M-H #4 OK TO BACKFILL. WILL REQUIRE VERIFICATION OF GRADE VACCUM TEST ON M-H'S TESTING AT LATER DATE. OK TO COVER |
| 10/15/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ UP TO M-H #4 OK TO COVER SUBJECT TO VERIFICATION OF GRADE. VACUUM TEST ON M-H. |
| 10/14/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ APPROX. 165' - SUBJECT TO TESTING./ VACUUM TEST ON MANHOLES 1,2,3 OK. NEEDS LISTING ON MH FROM HAYDEN. |
| 10/13/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ 65' EAST OF MH. #3 - CONTRACTOR WILL PROVIDE VERIFICATION OF GRADE TEST AT LATER DATE. ALSO VACUUM TEST AT LATER DATE. |
| 10/10/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000* |
| 10/09/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
1) G5 TO M-H #3 OK TO COVER WILL REQUIRE VERIFICATION OF GRADE 2) CONTRACTOR WILL TEST AT LATER DATE 3) WILL REQUIRE VACCUM TEST ON M-H'S |
| 10/08/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Partial Approval |
IVRS - Inspection 0000*/ WILL REQUIRE VERIFICATION OF GRADE. CONTRACTOR WILL TEST AT LATER DATE. |
| 10/07/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ REVISED APPROVED PLAN ON JOB BY WILDAV. |
| 10/06/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ FROM M.H.? APPROX 125' SOUTH - COVERED WITHOUT INSP. - CONTRACTOR WILL UNCOVER BEFORE FINAL IS GIVEN. TALKED WITH MIKE. WILL REQUIRE VERIFICATION OF GRADE ON COMPLETE SEWER AND TESTING BEFORE FINAL IS GIVEN. VACUUM TEST REQUIRED ON M.H.'S. 10/06/03 - 3:00 PM - 28' SDR 35 - NOT READY. UNABLE TO COMPLETE INSPECTION. NO APPROVED REVISED PLANS ON JOB. APPROVED PLAN CALLS FOR M.H. #2. |
| 10/05/2003 |
PLUMBING - SEWER HCS CONNECT |
|
Denied |
IVRS - Inspection 0999* |