Inspection Status: Approved
Inspection History: PLUMBING - ROUGH, SOIL
| Date |
Description |
Inspector |
Results |
Comments |
| 06/18/2003 |
PLUMBING - ROUGH, SOIL |
|
Approved |
IVRS - Inspection 0000* |
| 06/16/2003 |
PLUMBING - ROUGH, SOIL |
|
Denied |
1) AB SUBMITTALS ON SITE. CHANGED FROM A HAND SINK TO A WASH BASIN DOES NOT AUTOMATICALLY CHANGE THE DFU'S FROM TWO TO ONE. I NEED TO CHECK THE SUBMITTALS TO SEE IF THE TAIL PIECE IS 1 1/4" OR 1 1/2" BECAUSE P-2 SCHEMATIC DESCRIBES THE WASH BASIN AS A ELKAN SINGLE COMPARTMENT SINK |
| 06/10/2003 |
PLUMBING - ROUGH, SOIL |
|
Denied |
1) I BELIEVE THE DELTA ONE REVISION WAS APPROVED IN ERROR. A SINK AND A LAVATORY ARE NOT INTERCHANGEABLE, AS NOTED ON THE WASTE AND VENT SCHEMATIC: LAVATORY WASTER=1 1/4", SINK WASTER=2". A HAND SINK IS A TWO DRAINAGE FIXTURE UNIT FIXTURE |
| 06/04/2003 |
PLUMBING - ROUGH, SOIL |
|
Denied |
IVRS - Inspection 0999*/ 1) CAN ONLY HAVE 8 FIXTURE UNITS ON 2" HORIZONTAL WASTE LINE 2) WILL REQUIRE A REVISED AND APPROVED DRAWING ON WASTE AND VENT SYSTEM BEFORE THE NEXT INSPECTION 3) RE-TEST SYSTEM |