Inspection Status: Approved
Inspection History: REINFORCED MASONRY PRE-GROUT
| Date |
Description |
Inspector |
Results |
Comments |
| 05/06/2004 |
REINFORCED MASONRY PRE-GROUT |
|
Approved |
IVRS - Inspection :*/ 1) TOP OUT AT SOUTH UNIT AND 2ND LFIT AT NORTH UNIT |
| 04/28/2004 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |
IVRS - Inspection :* OK 1ST LIFT NORTH BUILDING. OK SOUTH 2ND LIFT |
| 04/22/2004 |
REINFORCED MASONRY PRE-GROUT |
|
Partial Approval |