Inspection History Details
Inspection Status: Approved
Inspection History: ENGINEERING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/14/2003 | ENGINEERING - FINAL | Approved | C OF O APPROVED. | |
| 10/01/2003 | ENGINEERING - FINAL | Partial Approval | Temporary C of O issued. 1. Bicycle rack and lockers are on back order. 2. Drain spouts are not completed. 3. Revison for handicap ramp has been submitted and waiting for approval. |
|
| 09/23/2003 | ENGINEERING - FINAL | Denied | 1. Provide bicycle racks and lockers per plan. 2. Address N. retention/detention area. 3. Complete down spouts with rock rip rap. 4. Revision on handicap ramp. 5. Backfill footing for new screen wall. |
|
| 09/11/2003 | ENGINEERING - FINAL | Denied | PARTIAL APPROVAL, FINAL NOT TO BE GIVEN UNTIL ALL EXTERIOR WORK IS COMPLETED. |