Inspection Status: Approved
Inspection History: PLUMBING - GAS PRESS TEST FNL
| Date |
Description |
Inspector |
Results |
Comments |
| 09/05/2003 |
PLUMBING - GAS PRESS TEST FNL |
|
Approved |
|
| 07/24/2003 |
PLUMBING - GAS PRESS TEST FNL |
|
Partial Approval |
1) TEST-OK 2) OK-TO COVER 3) WILL REQUIRE VALVES AND FLUE AT TIME OF FINAL |
| 07/22/2003 |
PLUMBING - GAS PRESS TEST FNL |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ PLEASE NOTE: WALLS HAVE BEEN COVERED W/OUT INSP. 1) PLUMBING INTERMEDIATE HAS NOT BEEN APPROVED. 2) PARTIAL ONLY UNDERGROUND GAS ONLY 1-1/4 TO 2ND FLOOR COVERED AT THIS TIME. PLEASE REMOVE FOR INSP. ALSO PLEASE PROVIDE ACCESS TO ROOF FOR INSP. NO SUPER ON JOB. |