Inspection Status: Approved
Inspection History: FRAMING
| Date |
Description |
Inspector |
Results |
Comments |
| 03/21/2003 |
FRAMING |
|
Approved |
IVRS - Inspection 0000* |
| 03/19/2003 |
FRAMING |
|
Denied |
IVRS - Inspection 0999*/ 1) A TEST IS REQUIRED ON DWV SYSTEM TO TOP OF VENT 2) NAIL PROTECT ALL FRAMING PENETRATIONS < 1 1/4" FROM SURFACE 3) LATH AND WINDOWS MUST BE IN TO APPROVE FRAMING 4) INSTALL T&P LINE 5) COMPLETE GAS AND PROVIDE AIR TEST 10 PSI MINIMUM 6) PROVIDE ENGINEER ANALYSIS OF WINDOW BEARING TOP CHORD 7) COMPLETE FRAMING AT KITCHEN WINDOW 8) MAKE UP GROUND IN ELECTRIC BOXES |
| 03/12/2003 |
FRAMING |
|
Not ready for Inspection |
IVRS - Inspection 0000* |