Inspection Status: Approved
Inspection History: PLUMBING - INTERMEDIATE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/22/2004 |
PLUMBING - INTERMEDIATE |
|
Approved |
IVRS - Inspection 0000*/ WTR TEST WASTE AND VENT THRU ROOF APPROVED. H20 60 PSI TEST APPROVED. WILL NEED TO SEE CLOSET FLANGES PRIOR TO SETTING STOOLS. |
| 01/21/2004 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 01/20/2004 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
IVRS - Inspection 0000* |
| 01/16/2004 |
PLUMBING - INTERMEDIATE |
|
Not ready for Inspection |
IVRS - Inspection 0000*/ 1) PROVIDE C/O AT UPPER STOOL. 2) SUPPORT ALL PIPING WITH APPROVED DEVICES. 3) USE FITTINGS APPROVED FOR DRAINAGE. 4) YARD WATER TO HAVE PRESSURE TEST. 5) H20 IN BLDG TO HAVE PRESSURE TEST. 6) H20 HOT AND COLD TO MAKE SEPERATION. 7) DRAIN ARMS TO BE ¼" PER FOOT FALL. 10 PSI TEST ON GAS PIPING FROM METER TO ROOF TOP UNIT, AND DRYER LOCATION APPROVED. |