Inspection History Details
Inspection Status: Approved
Inspection History: GRADING - FINAL
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 03/15/2006 | GRADING - FINAL | Approved | Received letter of asibuilt from engineer, project approved. | |
| 11/22/2005 | GRADING - FINAL | Denied | 1. SUBMIT REVISED DEVELOPMENT AND GRADING PLANS TO THE CITY OF TUCSON DEVELOPMENT SERVICES ZONING AND ENGINEERING DIVISIONS FOR REVIEW AND APPROVAL. (SEE GRADING PLAN NOTE 8 AND 20.) THE REVISED PLANS MUST SHOW ALL REVISIONS AND AS-BUILT CONDITIONS INCLUDING: 1- ALL MODIFICATIONS TO THE SITE DRAINAGE. 2- DRAINAGE FLOW PATTERNS. 3- ADDITIONS OF SIDEWALK SCUPPERS AND UNDERGROUND PIPES 4- MODIFICATIONS TO SIDEWALKS. 5- ADDITIONS OF STAIRS AND RAMPS 6- PLACEMENT OF GARAGES 7- MODIFICATIONS TO PARKING SPACE LOCATIONS. 8- ALL OTHER MODIFICATIONS NOT SHOWN ON THE ORIGINAL APPROVED PLANS. 2. PROVIDE A LETTER OF CERTIFICATION THAT THE PROJECT WAS CONSTRUCTED IN SUBSTATIAL CONFORMANCE WITH THE APPROVED PLANS AFTER THE REVISED PLANS HAVE BEEN APPROVED BY THE CITY OF TUCSON. (SEE GRADING NOTE 21.) 3. COMPLETE CONSTRUCTION AND STABILIZATION OF RETENTION/DETENTION BASINS. 4. PROVIDE AN ARIZONA REGISTERED PROFESSIONAL ENGINEERS CERTIFIED INSPECTION REPORT FOR RETENTION/DETENTION BASINS "B", "C" AND "D". THE LETTER MUST ADDRESS INFILTRATION/PERCOLATION RATES. (SEE GRADING NOTE 31) 5. PROVIDE SIDEWALK SCUPPERS AND CORRECT ALL DRAINAGE FLOW PROBLEMS TO ASSURE ALL 10-YEAR STORMWATER DRAINAGE FLOWS ARE BENEATH SIDEWALKS. THIS APPLYS TO ALL AREAS AT THIS PROJECT. 6. MAXIMIZE STORM WATER HARVESTING BY DEPRESSING ALL LANDSCAPED AREAS 6" MAX. APPROPRIATE STORM WATER HARVESTING WILL PREVENT STORMWATER FLOW ACROSS SIDEWALKS AND PROVIDE POSITIVE DRAINAGE TO THE RELEASE POINTS AT THE SIDEWALK SCUPPER LOCATIONS. (SEE GRADING PLAN NOTE 30.) 7. REPLACE THE SUBSTANDARD CURB NEAR BUILDING #8. 8. COMPACT THE SOIL OR ADD SLURRY TO AREAS UNDER THE SIDEWALKS WHERE SLEEVES OR DRAINAGE PIPES WERE INSTALLED AFTER THE SIDEWALKS WERE CONSTRUCTED. 9. PROVIDE TYPE II SIDEWALK SCUPPERS AT THE OUTLET TO BASIN "B AND AT THE CUL-DE -SAC NEAR BUILDING #2. THE SIDEWALK SCUPPERS MUST BE CONSTRUCTED TO COT/PC STANDARD DETAIL 205. 10. STABILIZE THE CONSTRUCTION STAGING SITE LOCATED ON THE AREA FOR PHASE II OF THIS PROJECT. 11. CORRECT ALL TRIP OR SAFETY HAZARDS ASSOCIATED WITH THE DRAINAGE SWALES LOCATED IMMEDIATELY ADJACENT TO SIDEWALKS. |
|
| 02/18/2005 | GRADING - FINAL | Denied | NOT READY FOR INSPECTION. CONTRACTOR CALLED INSPECTION TO DISCUSS PHASE PLAN REQUIREMENTS. |