Permit: T03BU03091

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
10/29/2008 GRADING - FINAL Approved Allitems on punch list dated 10/30/06 are complete, as-built drawing submitted.
project complete.
12/08/2006 GRADING - FINAL Denied RE-SENT EMAIL AND EMAIL TO PAUL MACHADO
12/07/2006 GRADING - FINAL Denied NO CHANGES
10/30/2006 GRADING - FINAL Denied THE FINAL GRADING INSPECTION WAS CONDUCTED IN REFERENCE TO THE GRADING PLAN THAT WAS APPROVED BY THE CITY OF TUCSON (PAUL MACHADO) ON 3-21-04.

THE FOLLOWING DEFICIENCIES WERE NOTED FOR THIS PROJECT.

1. CONSTRUCT SITE TO GRADING PLAN SPECIFICATIONS OR SUBMIT A REVISED GRADING PLAN TO THE CITY OF TUCSON, DEVELOPMENT SERVICES ENGINEERING AND ZONING DIVISIONS, FOR REVIEW AND APPROVAL.
2. PROVIDE A LETTER OF CERTIFICATION FROM AN ARIZONA REGISTERED P.E. THAT CERTIFYS THAT THE PROJECT AND DRAINAGE IMPROVEMENTS WERE CONSTRUCTED TO THE APPROVED GRADING PLANS AND WILL FUNCTION AS DESIGNED.
3. LOTS 38-40 AND 45-48 PAD ELEVATIONS ARE NOT CONSISTENT WITH THE ELEVATIONS SHOWN ON THE GRADING PLAN. THESE PAD ELEVATIONS APPEAR TO BE APPROXIMATELY 2 FEET HIGHER THAN ELEVATIONS SHOWN ON THE APPROVED PLANS. THE DRIVEWAYS FOR THESE LOTS EXCEED 15% SLOPE.
4. FILL IN LOW SPOTS AND ADDRESS STANDING WATER IN BASIN #1.
5. PROVIDE 4:1 SLOPES WITH A 2' BENCH AT TOP OF SLOPE ON ALL SIDES OF BASIN #2. SEE DETAIL I, PAGE 3 OF GRADING PLAN.
6. REPAIR EROSION DAMAGE ON 8% ACCESS RAMP IN BASIN #2.
7. PROVIDE A DETAIL THAT SHOWS THE ROCK PLACED IN THE CENTER OF THE RETENTION/DETENTION BASIN #2, AND DRESS UP THE BASIN BOTTOM.
8. PROVIDE DRAINAGE SWALE AT SOUTH SIDE OF LOT #24.
9. REPAIR EROSION DAMAGE AT DRAINAGE CHANNEL NEAR SOUTHWEST CORNER OF LOT #24.
10. PROVIDE A 4' SIDEWALK SCUPPER AT THE SOUTHEAST CORNER OF THE PROJECT AS SHOWN IN DETAIL G., AND MATCH THE INCOMING DRAINAGE SWALE TO THE SCUPPER WIDTH.
09/19/2006 GRADING - FINAL Denied