Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit: T03BU02831

Inspection Status: Approved

Inspection History: GRADING - FINAL

Date Description Inspector Results Comments
04/07/2006 GRADING - FINAL Approved
03/15/2006 GRADING - FINAL Not ready for Inspection 1) COMPLETE OVERHEAD PERKING STRUCTURES
2) COMPLETE LANDSCAPING
3) INSTALL RIP RAP AT CURB OPENINGS IN ACCORDANCE WITH THE APPROVED GRADING PLAN
4) CLARIFY WHAT IS REQUIRED FOR THE WALL OPENINGS AT THE SE CORNER OF SITE SHOWN ON THE GRADING PLAN.
03/03/2006 GRADING - FINAL Not ready for Inspection FINAL GRADING DENIED, SITE NOT READY FOR INSPECTION.
12/09/2005 GRADING - FINAL Not ready for Inspection 1) SWEEP UP TRACKING OFF ADJACENT ROADWAYS.
2) A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD STATING THAT THE RET/DET BASIN ON SITE WAS BUILT ACCORDING TO THE APPROVED PLANS AND COMPLY WITH PRESCRIBED STANDARDS.
3) ANY CHANGES AND/OR REVISIONS TO THE APPROVED GRADING PLAN MUST BE SHOWN AND APPROVED BY THE ENGINEER OF RECORD AND THE CITY OF TUCSON, ENGINEERING SECTION. AN APPROVED COPY OF THE PLAN MUST BE MADE AVAILABLE TO THE INSPECTOR DURING THE FINAL GRADING INSPECTION.
10/25/2005 GRADING - FINAL Not ready for Inspection 1) ENSURE SEDIMENT AND WASTE MATERIALS (CONCRETE, MORTAR ECT.) ARE KEPT ON SITE PRIOR TO PROPER DISPOSAL.
2) ALL TRACKING OF DIRT AND DERIS ON TO PUBLIC ROADWAYS MUST BE SWEPT UP.
3) CALL THE CITY OF TUCSON, DEV SERVICES, ENGINEERING SECTION (MIKE RUSSO 240-9859) TWO WEEKS PRIOR TO YOUR EXPECTED BUILDING OCCUPANCY DATE, SO A SITE INSPECTION CAN BE ACCOMPLISHED AND ANY PUNCH LIST ITEMS CAN BE ADDRESSED PRIOR TO OCCUPANCY.
4) A FINAL GRADING INSPECTION FOR PERMIT # T03BU02831 MUST BE ACCOMPLISHED AND APPROVED PRIOR TO OCCUPANCY.
5) ANY SOIL OR SEDIMENT THAT LEAVES THE SITE DUE TO DRAINAGE AND THE LACK OF STORM WATER CONTROLS, MUST BE CLEANED IMMEDIATELY.